Winters Glow Storage
155.2 MW generation in Runnels, TX · In queue since October 2024 · Proposed COD April 2029
155.2 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 6m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-17
Projected COD moved
2 times
Jun 2028 → Apr 2029
Net change
+10 months
first report to latest
Capacity
155 → 155 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue, Facility Study phase
Proposed commercial operation date per ERCOT filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity available. No press releases or corporate announcements found to identify a parent operating company. The LLC name suggests a project-specific entity but no parent company could be determined from available sources.
Status: LBNL shows active queue status in Facility Study phase. No news coverage found to provide additional ground-truth status updates beyond the queue filing.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Winters Glow Storage project is a proposed 155.29 MW battery storage project located in Runnels County, Texas. Developed by Winters Glow Storage, LLC, the project is currently in the ERCOT interconnection queue as entry ERCOT-28INR0199, with a queue entry date of October 29, 2024. The proposed commercial operation date is September 19, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 155.29 MW of battery storage capacity. The point of interconnection is at the tap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF. The project is listed as active within the ERCOT queue.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Runnels
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Winters Glow Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.