Winters Glow Solar (ERCOT-28INR0198) — Project Summary

Queue ID
ERCOT-28INR0198
Capacity
301.6 MW
Technology
Solar+Battery
Status
active
Location
Runnels, TX
Region
ERCOT
Developer
Winters Glow Solar, LLC
IA Status
Facility Study

Winters Glow Solar

ERCOT-28INR0198BetaActiveSolarBatteryERCOTLBNL + Live

301.6 MW hybrid in Runnels, TX · In queue since October 2024 · Proposed COD April 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

301.6 MW

Capacity

1

Components

Solar

2y 1m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 6m

Facilities Study50%
Queue EntryOct 29, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-04-17

Queue history
28INR0198 · 24 monthly ERCOT reports, Oct 2024 – Sep 2026

Projected COD moved

2 times

Jun 2028 → Apr 2029

Net change

+10 months

first report to latest

Capacity

253 → 302 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedOct 29, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 17, 2029
From queue filing
Developer in saved assessment
Winters Glow Solar, LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at Facility Study stage with no IA executed; no construction, permitting or financing announcements found. A companion storage project (28INR0199, Winters Glow Storage) is also queued.
Financing
Not recorded
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-28inr0198
  2. cleanview.co/power-projects/planned/solar-farms/texas/28INR0198/winters-glow-solar
  3. texas-biz.com/co/winters-glow-solar-llc
  4. ercotqueue.com/project/28INR0199

Commercial operation date: Only queue-derived data exists. Cleanview says 'Expected online 2029' and interconnection.fyi lists April 17, 2029, but both appear to mirror the LBNL/ERCOT filing rather than an independent developer-backed target.

Developer: No press release or news names a parent or operating company. Only the project-LLC name appears (LBNL, interconnection.fyi, Texas business registry). It is a foreign LLC registered in Texas on 2024-08-27, and its sponsor is unidentified.

Status: LBNL and interconnection.fyi both show the project as active in the queue. No news indicates withdrawal, construction or an executed IA.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Winters Glow Solar is a proposed solar generation project located in Runnels County, Texas, with a total capacity of 252.94 MW. Developed by Winters Glow Solar, LLC, the project consists entirely of solar photovoltaic generation. It is currently active in the ERCOT interconnection queue as project ERCOT-28INR0198, with a queue entry date of October 29, 2024, and a proposed commercial operation date of September 19, 2028. The project's interconnection status is currently in the Facility Study phase.

The proposed point of interconnection is the tap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF. The project has been mentioned in recent news coverage related to the electric grid.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Runnels

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Winters Glow Solar, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

tap 345kV 1444 BROWN SWITCH - 11406 CENTRAL BLUFF

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.