Tapaderos Storage
207 MW generation in Young, TX · In queue since November 2024 · Proposed COD September 2028
207 MW
Capacity
1
Components
Battery
2 years
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-19
Projected COD moved
1 time
Jun 2028 → Sep 2028
Net change
+3 months
first report to latest
Capacity
207 → 207 MW
changed in the reports
Latest stage
Screening started
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue and began Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity available. No press releases or corporate announcements found to identify a parent operating company. Entity name suggests project-specific LLC but no parent company identified.
Status: LBNL shows active status in Facility Study phase. No news coverage found to indicate construction activity, financing, or status changes.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Tapaderos Storage (ERCOT queue ID 28INR0196) is a proposed 207 MW energy storage development project in Young County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Tapaderos Storage, LLC. Although the queue classifies it under the Solar+Battery technology category, its only listed component is a 207 MW battery storage system, and no solar capacity is specified. The project would connect to the grid at a tap on the 345 kV transmission line between the Graham SES (#1430) and Long Creek (#1435) substations.
The project entered the ERCOT interconnection queue on November 19, 2024, and has a proposed commercial operation date of September 19, 2028. Its interconnection agreement status is listed as Facility Study, but the project's overall queue status is currently suspended.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Mar 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Young
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tapaderos Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
TAP 345kV #1430 GRAHAM SES - #1435 LONG CREEK
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Tapaderos Storage
Data-driven briefing on Tapaderos Storage — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.