Brookesmith Storage
351 MW storage in Brown, TX · In queue since April 2025 · Proposed COD May 2029
351 MW
Capacity
1
Components
Battery
1y 7m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-07
Projected COD moved
1 time
Sep 2028 → May 2029
Net change
+8 months
first report to latest
Capacity
351 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/28INR0166/brookesmith-storage
- cleanview.co/power-projects/developers/origis-energy
- interconnection.fyi/project/ercot-28inr0166
- interconnection.fyi/projects/state/TX
Commercial operation date: Only the LBNL proposed COD (2029-05-07) is available. Cleanview's 'expected to come online in May 2029' matches it and appears to be derived from the queue data, so it is not independent confirmation. No developer press release or news gives a separate target.
Developer: Cleanview's Origis Energy pipeline page lists Brookesmith Storage (351 MW, Battery) among Origis's top projects, which indicates the LBNL project LLC is an Origis vehicle. This is a single aggregator source, not a press release. The Intersect Power item in the results concerns the separate Radian project and was not used.
Status: LBNL and interconnection.fyi both show the project as active, with ia_status at Facility Study and no IA date. No contradicting withdrawal or construction signals were found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Brookesmith Storage project is a proposed 351 MW hybrid battery energy storage project located in Brown County, Texas. Developed by Brookesmith Storage LLC, the project consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-28INR0166, with a queue entry date of April 1, 2025, and a proposed commercial operation date of May 7, 2029.
The point of interconnection for the Brookesmith Storage project is the Tap Brown Switch #1444 – Russell Gap Switch #3348. The project is listed as a hybrid project in the ERCOT queue, combining battery storage with other unspecified generation technologies to reach its total capacity of 351 MW.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Brown
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Brookesmith Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Brown Switch #1444 – Russell Gap Switch #3348
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.