Pamela Heights I
101.65 MW storage in Harris, TX · In queue since September 2024 · Proposed COD December 2026
101.65 MW
Capacity
1
Components
Battery
2y 2m
In Queue
IA Executed
IA Phase
Signed Oct 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 1m
IA → COD
1y 2m
Total Duration
1y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2026-12-18
Projected COD moved
3 times
Jun 2026 → Dec 2026
Net change
+6 months
first report to latest
Capacity
100 → 102 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT
Proposed commercial operation date per LBNL queue
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of July 2026. No independent news or press releases found to validate or contradict this target date.
Developer: Only the LBNL filing entity is known. No press releases or corporate announcements found to identify a parent operating company. The LLC naming pattern suggests a project-specific entity, but no parent company could be confirmed.
Status: LBNL shows active status with interconnection agreement executed in October 2025, indicating the project has cleared a major regulatory milestone and remains on track.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Callisto 1C Energy Center is a proposed 103.8 MW battery storage project located in Harris County, Texas. Developed by Tempus Power Management LLC, the project is interconnected within the Electric Reliability Council of Texas (ERCOT) region. It entered the ERCOT interconnection queue as project number ERCOT-28INR0154 on September 10, 2024, with a proposed commercial operation date of July 20, 2026. The project's interconnection status is currently in the Facility Study phase.
The proposed project consists of 103.8 MW of battery storage capacity. Recent news coverage has discussed the development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Harris
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pamela heights I Energy Center LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#47150 HOC 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PRO_RN
- POI Substation
- H.O. Clarke Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Pamela Heights I
Data-driven briefing on Pamela Heights I — fleet, generation, financial, and news signals.
Pamela Heights I Energy Center
Data-driven briefing on Pamela Heights I Energy Center — fleet, generation, financial, and news signals.
Energy Center
Data-driven briefing on Energy Center — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.