River Boat Storage
207.02 MW generation in Mitchell, TX · In queue since October 2024 · Proposed COD September 2028
207.02 MW
Capacity
1
Components
Battery
2y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-09-25
Projected COD moved
1 time
Jun 2028 → Sep 2028
Net change
+3 months
first report to latest
Capacity
207 → 207 MW
changed in the reports
Latest stage
Screening started
last listed Apr 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue and began Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing identifies Champion Creek Storage, LLC as developer. No news coverage or corporate announcements found to identify a parent operating company or confirm this is a project-specific LLC.
Status: LBNL shows active queue status in Facility Study phase. No news or public announcements found regarding project progression, permitting, or construction plans.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
River Boat Storage (queue ID ERCOT-28INR0133) is a proposed energy storage development project in Mitchell County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Champion Creek Storage, LLC is developing the generation project, which has a total capacity of 207.02 MW. The queue classifies the technology as Solar+Battery, but the listed components include only a battery component of 207.02 MW, and no solar capacity is specified. The project would connect at a point of interconnection on the 345 kV line tap between the Cattlemen 5 (10053) and Gasconades Creek (76030) buses.
The project entered the ERCOT interconnection queue on October 1, 2024, and has a proposed commercial operation date of September 25, 2028. Its interconnection agreement process is at the Facility Study stage. The project's queue status is listed as suspended.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Apr 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Mitchell
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Champion Creek Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 10053 Cattlemen 5 - 76030 Gasconades Creek
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
River Boat Storage
Data-driven briefing on River Boat Storage — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.