Jalisco Peaker
183.6 MW generation in Nueces, TX · In queue since August 2024 · Proposed COD May 2029
183.6 MW
Capacity
1
Components
Gas
2y 3m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-05-31
Projected COD moved
0 times
May 2029 → May 2029
Net change
0 months
first report to latest
Capacity
184 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue in Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of May 2029. No independent news or press releases found to validate or contradict this target date.
Developer: HEP Power Generation, LLC is the filing entity in LBNL queue. No news coverage found to identify if this is a shell LLC or operating parent company, or to reveal any ownership structure.
Status: LBNL status shows Active with Facility Study phase. No news coverage found to indicate project progression beyond interconnection study phase.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Jalisco Peaker is a proposed natural gas-fired generation project located in Nueces County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by HEP Power Generation, LLC, the project has a total planned capacity of 183.6 megawatts (MW), consisting entirely of gas-fired generation. As its name indicates, the facility is intended to operate as a peaking resource. The project is designed to connect to the grid at the 8475 JAVELINA4A 138 kV point of interconnection.
The development project is listed in the ERCOT interconnection queue under the identifier ERCOT-28INR0121, with a queue entry date of August 16, 2024. Its status in the queue is active, and it is currently in the Facility Study phase of the interconnection process. The project has a proposed commercial operation date of May 31, 2029.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nueces
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
HEP Power Generation, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8475 JAVELINA4A 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.