RAYBURN ENERGY STATION II Gas (TEF-Due Diligence)
570 MW generation in Grayson, TX · In queue since January 2025 · Proposed COD February 2028
570 MW
Capacity
1
Components
Gas
1y 10m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-02-26
Projected COD moved
0 times
Feb 2028 → Feb 2028
Net change
0 months
first report to latest
Capacity
570 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Rayburn Electric executed a TEF loan agreement with the PUCT to finance the 570 MW RES II.
rayburnelectric.comRES II is scheduled to come online in June 2028.
rayburnelectric.comResearch sources and reasoning (5 recorded sources)
high confidence at research time
- rayburnelectric.com/news-releases/rayburn-electric-cooperative-executes-texas-energy-fund-loan-agreement-for-rayburn-energy-station-ii/
- rayburnelectric.com/news-releases_category/rayburn-energy-station-2/
- dallasexpress.com/metroplex/first-electric-co-op-wins-411m-texas-energy-fund-loan-for-sherman-power-plant/
- interconnection.fyi/project/ercot-28inr0108
- ercotqueue.com/project/28INR0108
Commercial operation date: Rayburn Electric's June 4, 2026 press release says RES II "is scheduled to come online in June 2028," versus the LBNL proposed COD of 2028-02-26. The gap is only about 4 months, so the sources agree to within a year.
Developer: The LBNL filing entity is Rayburn Energy Station LLC, the project-level entity. The press release names Rayburn Electric Cooperative as the owner and operator ("locally owned and operated"), and aggregator sites list Rayburn Country Electric Cooperative, Inc.
Status: LBNL shows active, and the June 2026 TEF loan execution confirms the project is advancing. No source shows it under construction yet or operational. The interxdata 'operational' label looks erroneous.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Rayburn Energy Station II Gas (TEF-Due Diligence) project is a proposed 570 MW gas-fired generation project located in Grayson County, Texas. The developer is Rayburn Energy Station LLC. This project is in the ERCOT interconnection queue as entry ERCOT-28INR0108, with a queue entry date of January 13, 2025, and a proposed commercial operation date of February 26, 2028. An Interconnection Agreement (IA) was executed on December 22, 2025.
The proposed project is linked to the existing Rayburn Energy Station LLC operating plant (EIA ID 58005).
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Grayson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Rayburn Energy Station LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Double Tap 138 kV Haggerty (12677) - Progress Park (#12678) & Haggerty - Winding Oaks Switch
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.