Vazlon Solar SLF
211.41 MW hybrid in La Salle, TX · In queue since October 2024 · Proposed COD June 2028
211.41 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-30
Projected COD moved
0 times
Jun 2028 → Jun 2028
Net change
0 months
first report to latest
Capacity
211 MW
unchanged in the reports
Latest stage
Screening started
last listed Aug 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue at Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of June 2028. No independent news or press releases found to validate or contradict this target date.
Developer: LBNL lists 'Vazlon Energy LLC' as developer. No news coverage found to confirm whether this is an operating company or project-specific shell entity, or to identify any parent organization.
Status: LBNL status shows 'active' with IA status at Facility Study stage. No news coverage found to provide ground-truth updates on permitting, financing, or construction progress.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Vazlon Solar SLF (queue ID ERCOT-28INR0101) is a proposed solar and battery storage hybrid development project in La Salle County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Vazlon Energy LLC is the developer, and the project has a total listed capacity of 211.41 MW. Its listed component is 211.41 MW of solar generation. Although the project is classified as a Solar+Battery hybrid, the data does not give a separate capacity figure for the battery storage portion. The proposed point of interconnection is the 8619 Encinal – 8627 Lemay Box Bay 138 kV transmission line.
The project entered the ERCOT interconnection queue on October 1, 2024, with a proposed commercial operation date of June 30, 2028. Its interconnection agreement status is listed as Facility Study, meaning it has not yet executed an interconnection agreement. The project's overall queue status is currently recorded as suspended.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Aug 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
La Salle
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Vazlon Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
8619 Encinal - 8627 Lemay Box Bay 138kV line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Vazlon Solar SLF
Data-driven briefing on Vazlon Solar SLF — fleet, generation, financial, and news signals.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.