North Royal Thermal (TEF- Due Diligence) (ERCOT-28INR0087) — Project Summary

Queue ID
ERCOT-28INR0087
Capacity
479 MW
Technology
Gas
Status
active
Location
Lamar, TX
Region
ERCOT
Developer
Invenergy Energy Transition Development LLC
IA Status
Facility Study

North Royal Thermal (TEF- Due Diligence)

ERCOT-28INR0087BetaActiveGasERCOTLBNL + Live

479 MW generation in Lamar, TX · In queue since June 2024 · Proposed COD August 2030

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

479 MW

Capacity

1

Components

Gas

2y 5m

In Queue

Facility Study

IA Phase

COD target: 2030

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

6y 2m

Facilities Study50%
Queue EntryJun 13, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-08-01

Queue history
28INR0087 · 20 monthly ERCOT reports, Feb 2025 – Sep 2026

Projected COD moved

1 time

May 2029 → Aug 2030

Net change

+15 months

first report to latest

Capacity

479 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJun 13, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Aug 1, 2030
From queue filing
Developer in saved assessment
Invenergy
Filed as Invenergy Energy Transition Development LLC
Status at research time
Active
Active in the ERCOT queue: system study completed, facility study (FIS) started, no interconnection agreement yet. A PUCT NOI has been filed for a ~480 MW peaking plant, but there is no public construction or financing signal.
Financing
Not recorded
Research sources and reasoning (4 recorded sources)

low confidence at research time

  1. ercotqueue.com/project/28INR0087
  2. interchange.puc.texas.gov/Documents/56455_119_1399073.PDF
  3. cleanview.co/power-projects/planned/natural-gas-power-plants/texas/28INR0087/north-royal-thermal-tef--due-diligence
  4. app.nrgmap.com/queues/ercot-28inr0087

Commercial operation date: Only the LBNL/ERCOT filing date of 2030-08-01 is available. Cleanview (August 2030) and ercotqueue.com (Projected COD Q3 2030) repeat the same ERCOT GIS data rather than giving an independent developer-backed target. No press release or financing-backed date was found.

Developer: The LBNL filing entity is an Invenergy-named development LLC, so the parent is inferred from the entity name. A PUCT notice-of-intent filing (NOI 56455) was made by 'North Royal Energy Center LLC', which looks like the project-level entity. No source explicitly links it to Invenergy.

Status: LBNL and several trackers (nrgmap, interconnection.fyi, ercotqueue.com) show the project as active, with a Facility Study stage and no IA. The interxdata 'operational' label contradicts the filing data and was disregarded. ercotqueue.com puts build chance at 7%.

About

Saved background

Generated Oct 25, 2026

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

North Royal Thermal (TEF- Due Diligence) is a proposed natural gas-fired generation development project in Lamar County, Texas. The project, identified in the Electric Reliability Council of Texas (ERCOT) interconnection queue as ERCOT-28INR0087, has a total planned capacity of 479 megawatts (MW) consisting entirely of gas-fired generation. It is being developed by Invenergy Energy Transition Development LLC. The "TEF- Due Diligence" designation in its name may refer to the Texas Energy Fund, a state program supporting new dispatchable generation, but the project data does not confirm this.

The project entered the ERCOT interconnection queue on June 13, 2024, and remains active. It is currently in the Facility Study phase of the interconnection process. Its proposed point of interconnection is a tap on the 345 kV transmission line between the Moses (bus 1695) and Woodard (bus 11699) substations. The proposed commercial operation date is August 1, 2030.

Summary provenance

Summary generated Oct 25, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Lamar

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Invenergy Energy Transition Development LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 1695 MOSES_5 - 11699 WOODARD_5

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.