Indigo Solar 3
800 MW generation in Fisher, TX · In queue since October 2024 · Proposed COD November 2028
800 MW
Capacity
1
Components
Solar
2y 1m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-01
Projected COD moved
0 times
Nov 2028 → Nov 2028
Net change
0 months
first report to latest
Capacity
800 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/solar-farms/texas/28INR0067/indigo-solar-3
- ercotqueue.com/project/28INR0067
- fieldprospects.com/developers/indigo-solar-3/
- interconnection.fyi/projects/state/TX/fisher-county
Commercial operation date: Only the LBNL/ERCOT queue date (2028-11-01) exists. Cleanview's 'expected to come online in November 2028' repeats the queue data, not an independent developer signal, so it is not a separate confirmation.
Developer: The LBNL developer field just repeats the project name (a placeholder shell). No press release or news names a parent or operating company. Aggregators such as FieldProspects and ercotqueue.com echo the same name.
Status: LBNL lists the project as active, and the aggregator listings (interconnection.fyi, Cleanview) agree. No news indicates withdrawal or construction.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Indigo Solar 3 is a proposed 800 MW solar photovoltaic generation project located in Fisher County, Texas. The development project is listed in the interconnection queue of the Electric Reliability Council of Texas (ERCOT) under queue ID ERCOT-28INR0067, with Indigo Solar 3 identified as the developer. The project consists of a single solar component totaling 800 MW and does not include battery storage or other hybrid elements.
The project entered the ERCOT interconnection queue on October 29, 2024, and maintains an active status. Its proposed commercial operation date is November 1, 2028. As of the latest available data, the project is in the Facility Study phase of the interconnection process and has not yet reached an executed interconnection agreement. The proposed point of interconnection is a tap on the transmission line segment between Tankawa (Bus #1048) and Graham (Bus #1430).
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Fisher
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Indigo solar 3
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap Line Segment Tankawa (Bus #1048) to Graham (Bus #1430)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.