Bluefox Solar 2
401.8 MW generation in Matagorda, TX · In queue since March 2024 · Proposed COD January 2030
401.8 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-01-17
Projected COD moved
2 times
Sep 2028 → Jan 2030
Net change
+16 months
first report to latest
Capacity
402 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-28inr0063
- ercotqueue.com/project/28INR0063
- ercotqueue.com/developer/industrial-november-project-llc
- cleanview.co/planned-solar-projects/TX/28INR0063/bluefox-solar-2
- app.nrgmap.com/queues/ercot-28inr0063
Commercial operation date: Only the LBNL proposed COD of 2030-01-17 exists. Cleanview and interconnection.fyi repeat the same queue date and are not independent post-LBNL signals; no developer press release or news gives a different target.
Developer: All sources, including ercotqueue.com and infrasure.ai, name Industrial November Project LLC, which appears to be a queue-filing entity. No parent or operating company could be identified, so the LBNL name is retained.
Status: LBNL shows active with Facility Study and no IA date. ercotqueue.com, interconnection.fyi and NRG Map agree it is active. The interxdata 'operational' snippet conflicts with this and is disregarded as unreliable.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Bluefox Solar 2 is a proposed solar generation project with a total capacity of 401.8 MW. The project is located in Matagorda County, Texas, within the ERCOT region. It is being developed by Industrial November Project LLC.
The project is listed in the ERCOT interconnection queue as entry ERCOT-28INR0063, with a queue entry date of March 22, 2024. The proposed commercial operation date is January 17, 2030. The project's interconnection agreement status is currently in the Facility Study phase. The point of interconnection is #8754 Zoisite 345kV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Matagorda
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Industrial November Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#8754 Zoisite 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.