Sunrose Renewable Energy Solar SLF
309.88 MW hybrid in Austin, TX · In queue since April 2024 · Proposed COD July 2029
309.88 MW
Capacity
1
Components
Solar
2y 7m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-04
Projected COD moved
4 times
Dec 2027 → Jul 2029
Net change
+19 months
first report to latest
Capacity
301 → 310 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- sunroserenewableenergy.com/
- cleanview.co/power-projects/planned/solar-farms/texas/28INR0061/sunrose-renewable-energy-solar-slf
- ercotqueue.com/project/28INR0061
- interconnection.fyi/project/ercot-28inr0061
- app.nrgmap.com/queues/ercot-28inr0061
Commercial operation date: The only dated COD is the ERCOT queue's 2029-07-04, which aggregators such as Cleanview repeat ('Expected online 2029'). The developer site says the project 'could be operational as soon as 2028', but that is aspirational and not tied to financing or construction. The news-extracted 2026 COD belongs to Enbridge's 815 MW Sequoia Solar and was not used.
Developer: The project's own website and the queue trackers all name Sunrose Renewable Energy (LLC) as developer. The news-extracted 'Enbridge' attribution comes from an article about Sequoia Solar (815 MW), a different project, and nothing links Enbridge to this Austin County project, so it was rejected.
Status: LBNL and ercotqueue.com/nrgmap show the project as active with no IA, and the developer site calls it 'proposed'. The Interxdata 'operational' label contradicts every other source and was discounted. The 'construction' signal in the news facts comes from the unrelated Sequoia article.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Sunrose Renewable Energy Solar SLF is a proposed solar generation project located in Austin County, Texas, within the ERCOT region. Developed by Sunrose Renewable Energy LLC, the project has a total capacity of 300.88 MW, consisting entirely of solar photovoltaic generation. The project entered the ERCOT interconnection queue as entry ERCOT-28INR0061 on April 9, 2024, and has a proposed commercial operation date of December 31, 2029. Its interconnection status is currently in the Facility Study phase.
The proposed project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Austin
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Sunrose Renewable Energy LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV #44740 WALLIS - #44700 GEBHRT
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-19
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.