Pecan Ridge
150.79 MW hybrid in McCulloch, TX · In queue since December 2025 · Proposed COD June 2027
150.79 MW
Capacity
0
Components
5 months
In Queue
—
IA Status
COD target: 2027
Total Duration
1y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-30
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Pecan Ridge development project is a proposed 150.79 MW hybrid battery storage project located in McCulloch County, Texas. Developed by Luminous Energy Renewables LLC, the project consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0593, with a queue entry date of December 17, 2025.
The proposed commercial operation date for the Pecan Ridge project is June 30, 2027. The point of interconnection is at the 60386 HEARTLAN2A 69kV substation.
Generated from interconnection queue and public data sources
State
TX
County
McCulloch
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Luminous Energy Renewables LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
60386 HEARTLAN2A 69kV
Data Source
Live · ERCOT
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Pecan RidgeForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.