Limitless Energy Hub II (ERCOT-27INR0582) — Project Summary

Queue ID
ERCOT-27INR0582
Capacity
1238.25 MW
Technology
Gas
Status
active
Location
Wilbarger, TX
Region
ERCOT
Developer
Limitless Energy Hub II LLC
IA Status
Facility Study

Limitless Energy Hub II

ERCOT-27INR0582BetaActiveGasERCOTLBNL + Live

1,238.25 MW generation in Wilbarger, TX · In queue since November 2025 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

1,238.25 MW

Capacity

1

Components

Gas

1 year

In Queue

Facility Study

IA Phase

Signed Dec 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1 month

IA → COD

3 years

Total Duration

1 month

Construction50%
Queue EntryNov 5, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 31, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2028-12-01

Queue history
27INR0582 · 11 monthly ERCOT reports, Nov 2025 – Sep 2026

Projected COD moved

0 times

Dec 2028 → Dec 2028

Net change

0 months

first report to latest

Capacity

1238 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 5, 2025
Interconnection agreement signedDec 31, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 1, 2028
From queue filing
Developer in saved assessment
Limitless Energy Hub II LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at the Facility Study stage (IA/FIS pending). No construction or permitting milestone is publicly reported.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/natural-gas-power-plants/texas/27INR0582/limitless-energy-hub-ii
  2. ercotqueue.com/project/27INR0582
  3. app.nrgmap.com/queues/ercot-27inr0582
  4. interconnection.fyi/project/ercot-27inr0582
  5. datacenterdynamics.com/en/news/nextera-gets-federal-approval-to-build-10gw-of-natural-gas-power-in-texas-and-pennsylvania-for-data-centers/

Commercial operation date: Only the LBNL/ERCOT filing gives a specific date (2028-12-01). Cleanview's 'Expected online 2028' matches it but looks derived from the same queue data, so it is not an independent signal. No developer press release or news item gives a different target.

Developer: The queue filing and ercotqueue.com both name Limitless Energy Hub II LLC. The news extraction names NextEra Energy as applicant, but its source is a DCD article about a 10 GW FERC approval across Texas and Pennsylvania. Nothing in the findings ties that article to this 1.2 GW Wilbarger County project, so I did not use it to override the filing entity.

Status: LBNL and the ERCOT trackers (ercotqueue.com, NRG Map, interconnection.fyi) all show the project as active. interxdata's 'operational' label conflicts with the filing's is_operational=false and the Facility Study stage, so I discounted it.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Limitless Energy Hub II is a proposed 1238.25 MW gas-fired combined-cycle generation project located in Wilbarger County, Texas. Developed by Limitless Energy Hub II LLC, the project is in the ERCOT interconnection queue as entry ERCOT-27INR0582, with a queue entry date of November 5, 2025. The project has an active status and a proposed commercial operation date of December 1, 2028.

An Interconnection Agreement (IA) for the project was executed on December 31, 2025. The point of interconnection (POI) is the 6111 RILEY7B Substation at 345kV.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wilbarger

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Limitless Energy Hub II LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

6111 RILEY7B Substation 345kV

Data Source

LBNL + Live

ApplicantNextEra Energy±Data Center Dynamics · 2026-03-26
AgencyFERC±Data Center Dynamics · 2026-03-26
RulingApprovalData Center Dynamics · 2026-03-26
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-04-09

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.