Limitless Energy Hub I
1,238.25 MW generation in Wilbarger, TX · In queue since November 2025 · Proposed COD December 2028
1,238.25 MW
Capacity
1
Components
Gas
1 year
In Queue
Facility Study
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1 month
IA → COD
3 years
Total Duration
1 month
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 24–48 months
Proposed COD: 2028-12-01
Projected COD moved
0 times
Dec 2028 → Dec 2028
Net change
0 months
first report to latest
Capacity
1238 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (6 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-27inr0581
- ercotqueue.com/developer/limitless-energy-hub-i-llc
- ercotqueue.com/project/27INR0582
- bizapedia.com/tx/limitless-energy-hub-i-llc.html
- interchange.puc.texas.gov/search/documents/?controlNumber=35077&itemNumber=2364
- ercot.com/files/docs/2026/05/07/6.-EIR_Recommendation_Oncor_Combined-Set_1_Set_2_North_Central_South_Central_TX_Reliability_Project_Group2_RPG-May_2026.pdf
Commercial operation date: The LBNL/ERCOT queue shows a proposed COD of 2028-12-01. A May 2026 ERCOT reliability planning document lists Limitless Energy Hub I (Wilbarger, GAS, 1,238.3 MW) at 12/1/2028, but that is the same queue-derived date. No developer press release or financing-backed target was found.
Developer: Only the project-LLC name appears in the sources (ercotqueue, GridGlasses, Bizapedia Dallas TX registration). A PUC docket title mentions an '... Energy Hub, LLC' covering the Hub I and II projects, but the parent name is truncated and no operating company could be confirmed.
Status: LBNL shows 'active' and the ercotqueue/interconnection.fyi listings agree. No public evidence of a withdrawal or of construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Limitless Energy Hub I is a proposed 1238.25 MW gas-fired combined-cycle generation project located in Wilbarger County, Texas. Developed by Limitless Energy Hub I LLC, the project is in the ERCOT interconnection queue as entry ERCOT-27INR0581, with a queue entry date of November 5, 2025, and a proposed commercial operation date of December 1, 2028. The project has an Interconnection Agreement (IA) date of December 31, 2025, and its point of interconnection is the 6101 RILEY7A Substation 345kV.
The development project has been the subject of recent news coverage, with five articles categorized as industry news and deal-related announcements.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Limitless Energy Hub I LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6101 RILEY7A Substation 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesTOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Geothermal queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.