Limitless Energy Hub I
1,238.25 MW generation in Wilbarger, TX · In queue since November 2025 · Proposed COD December 2028
1,238.25 MW
Capacity
1
Components
Gas
8 months
In Queue
Facility Study
IA Phase
Signed Dec 2025
Queue → IA
1 month
IA → COD
3 years
Total Duration
1 month
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2028-12-01
Texas Energy Fund approved project financing as one of two projects approved under $7.2B loan program
sourceFacility Study phase with IA date of December 31, 2025 per LBNL queue
Proposed commercial operation date per LBNL interconnection queue
The Limitless Energy Hub I is a proposed 1238.25 MW gas-fired combined-cycle generation project located in Wilbarger County, Texas. Developed by Limitless Energy Hub I LLC, the project is in the ERCOT interconnection queue as entry ERCOT-27INR0581, with a queue entry date of November 5, 2025, and a proposed commercial operation date of December 1, 2028. The project has an Interconnection Agreement (IA) date of December 31, 2025, and its point of interconnection is the 6101 RILEY7A Substation 345kV.
The development project has been the subject of recent news coverage, with five articles categorized as industry news and deal-related announcements.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Limitless Energy Hub I LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6101 RILEY7A Substation 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26