Trailblazer Solar
323.02 MW generation in Nolan, TX · In queue since March 2026 · Proposed COD December 2027
323.02 MW
Capacity
0
Components
8 months
In Queue
—
IA Status
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-12
Projected COD moved
0 times
Dec 2027 → Dec 2027
Net change
0 months
first report to latest
Capacity
323 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-27inr0578
- cleanview.co/power-projects/planned/solar-farms/texas/27INR0578/trailblazer-solar
- interxdata.com/projects/trailblazer-solar-ercot-gis-report-27inr0578/
Commercial operation date: Only the LBNL/ERCOT queue date (proposed COD 2027-12-12) exists. Aggregator sites (interconnection.fyi, cleanview.co) merely echo it ('Expected online 2027'), and no independent news or press release gives a different target.
Developer: Only the LBNL filing entity (Trailblazer Infrastructure LLC) is available, repeated by aggregators. No press release identifies a parent or operating company. Search hits on 'Trailblazer' concern unrelated topics such as NASA's Lunar Trailblazer.
Status: LBNL lists the project as active with no IA and is_operational false, and interconnection.fyi and cleanview.co agree (planned, active). The lone 'operational' label is unsupported and contradicted by the queue date of March 2026.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Trailblazer Solar is a proposed photovoltaic solar development project located in Nolan County, Texas. Developed by Trailblazer Infrastructure LLC, the project has a total planned generating capacity of 323.02 megawatts (MW). It is designed to connect to the electric grid at the #11420 Sweetwater East Switch, a 345 kV point of interconnection.
The project is listed in the interconnection queue of the Electric Reliability Council of Texas (ERCOT) under queue ID ERCOT-27INR0578. It entered the queue on March 18, 2026, and currently holds an active status. The proposed commercial operation date is December 12, 2027. Information on the status of an interconnection agreement was not included in the available queue data.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Nolan
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Trailblazer Infrastructure LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#11420 Sweetwater East Switch 345 kV
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Trailblazer Solar
Data-driven briefing on Trailblazer Solar — fleet, generation, financial, and news signals.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.