Frizzle BESS
180.9 MW storage in Ward, TX · In queue since September 2025 · Proposed COD October 2027
180.9 MW
Capacity
1
Components
Battery
1y 2m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-18
Projected COD moved
0 times
Oct 2027 → Oct 2027
Net change
0 months
first report to latest
Capacity
180 → 181 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Proposed commercial operation date per ERCOT queue filing
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of October 2027. No independent news or research sources found to validate or contradict this date.
Developer: LBNL lists 'Frizzle BESS, L.L.C.' which appears to be a project-specific LLC. No news sources or corporate announcements found to identify the parent operating company or developer.
Status: LBNL status shows 'active' at Facility Study stage. No contradicting information or advancement signals found in public sources.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Frizzle BESS is a proposed 180.9 MW hybrid battery energy storage project located in Ward County, Texas. The project, developed by Frizzle BESS, L.L.C., consists of battery energy storage and other unspecified technologies. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0562, with a queue entry date of September 11, 2025, and a proposed commercial operation date of October 18, 2027.
The point of interconnection for Frizzle BESS is designated as #38143, TNSLVRLEAF1, 138kV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ward
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Frizzle BESS, L.L.C.
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#38143, TNSLVRLEAF1, 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.