Zeus Scurry Solar
503.54 MW hybrid in Scurry, TX · In queue since June 2025 · Proposed COD October 2028
503.54 MW
Capacity
1
Components
Solar
1y 5m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
Projected COD moved
1 time
Jul 2027 → Oct 2028
Net change
+15 months
first report to latest
Capacity
504 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (4 recorded sources)
low confidence at research time
- interconnection.fyi/project/ercot-27inr0529
- ercotqueue.com/project/27INR0529
- cleanview.co/power-projects/planned/solar-farms/texas/27INR0529/zeus-scurry-solar
- quicksandcheck.com/texas/scurry-county/
Commercial operation date: Only the LBNL proposed COD of 2028-10-01 exists. Cleanview, interconnection.fyi and Quicksand Check show 2028 / Oct 2028, but these appear to mirror the ERCOT queue data and are not independent developer-backed signals.
Developer: All sources name Scurry Solar, LLC, which is the queue filing entity. No press release or news item identifies a parent or operating company behind the 'Zeus' project name.
Status: LBNL shows active status with a Facility Study IA status and no IA date. Tracker sites (interconnection.fyi, ercotqueue.com, parcelandgrid) confirm active, in-study status. No evidence of construction or withdrawal.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Zeus Scurry Solar project is a proposed 503.54 MW solar generation project located in Scurry County, Texas. Developed by Scurry Solar, LLC, the project consists of photovoltaic solar technology and is interconnected within the Electric Reliability Council of Texas (ERCOT) region. The project entered the ERCOT interconnection queue as entry 27INR0529 on June 3, 2025, with a proposed commercial operation date of October 1, 2028.
The point of interconnection for the Zeus Scurry Solar project is the MHOS 345 kV Substation (#59911). The project is currently listed as active in the interconnection queue. The Zeus Scurry Solar project has appeared in recent news coverage regarding renewable energy development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Scurry
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Scurry Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
MHOS 345 kV Substation (#59911)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ANDMDSLR_ALL
- POI Substation
- Mhos Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.