Blackland Prairie 2 Energy Storage
102.1 MW storage in Travis, TX · In queue since March 2025 · Proposed COD December 2030
102.1 MW
Capacity
1
Components
Battery
1y 8m
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
5y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-01
Projected COD moved
2 times
Jun 2027 → Dec 2030
Net change
+42 months
first report to latest
Capacity
102 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT interconnection queue at Facility Study stage
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of December 2027. No independent news or press releases found to validate or contradict this target date.
Developer: LBNL lists 'Tempus power management LLC' as developer. No news coverage or corporate announcements found to confirm parent company structure or verify if this is a project SPV versus operating entity.
Status: LBNL status shows 'active' at Facility Study phase. No news coverage found to indicate construction start, financing, or permitting progress beyond queue position.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Blackland Prairie 2 Energy Storage project is a proposed 102.1 MW hybrid battery energy storage project located in Travis County, Texas. Developed by Tempus Power Management LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-27INR0486. The project entered the interconnection queue on March 24, 2025, with a proposed commercial operation date of December 1, 2027.
The project consists of battery energy storage and another unspecified technology. It is currently listed as active in the ERCOT interconnection queue. The point of interconnection is the 9328 Austrop 138kV location.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Travis
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tempus power management LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
9328 Austrop 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- WEBBER_WS_T1
- POI Substation
- Austrop Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Blackland Prairie 2 Energy Storage
Data-driven briefing on Blackland Prairie 2 Energy Storage — fleet, generation, financial, and news signals.
Prairie
Data-driven briefing on Prairie — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.