watermelon 3 energy storage
102.1 MW storage in Dallas, TX · In queue since January 2025 · Proposed COD March 2029
102.1 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Phase
COD target: 2029
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-01
Entered ERCOT queue in Facility Study phase
The proposed Watermelon 3 Energy Storage project is a 102.1 MW hybrid battery energy storage system located in Dallas County, Texas. The project, developed by Tempus Power Management LLC, is interconnected within the Electric Reliability Council of Texas (ERCOT) region under queue ID ERCOT-27INR0459. The project entered the interconnection queue on January 13, 2025, with a proposed commercial operation date of March 1, 2029.
The interconnection point of the project is a tap on the 2427 WATMLL_W5 to 2432 TRICRN1_5 345kV line ckt 1, approximately 1.6 miles from 2427 WATMLL_W5. The project's interconnection status is currently active within the ERCOT queue. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Dallas
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tempus power management LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap on 2427 WATMLL_W5 345.00 - 2432 TRICRN1_5 345.00 345kV line ckt 1. 1.6 miles from 2427 WATMLL_W5
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about watermelon 3 energy storageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.