Spinosa BESS
201.2 MW storage in Wichita, TX · In queue since April 2025 · Proposed COD May 2030
201.2 MW
Capacity
1
Components
Battery
1y 3m
In Queue
Facility Study
IA Phase
COD target: 2030
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-05-08
Entered ERCOT interconnection queue at Facility Study stage
The Spinosa BESS project is a proposed 201.2 MW hybrid battery energy storage project located in Wichita County, Texas. Developed by Spinosa Energy Center, LLC, the project entered the ERCOT interconnection queue as entry 27INR0412 on April 29, 2025. The current proposed commercial operation date is October 10, 2028.
The project is currently listed as active within the ERCOT queue. It involves battery energy storage and another unspecified technology. The point of interconnection is Tap 138 kV 1450 Pleasant Valley Switch - 1499 Parkway.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wichita
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Spinosa Energy Center, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV 1450 Pleasant Valley Switch - 1499 Parkway
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Pleasant Valley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.