Resaca Oasis Storage
200.7 MW storage in Cameron, TX · In queue since December 2024 · Proposed COD September 2027
200.7 MW
Capacity
1
Components
Battery
1y 7m
In Queue
IA Executed
IA Phase
Signed May 2025
Queue → IA
5 months
IA → COD
2y 4m
Total Duration
5 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-09-20
The Resaca Oasis Storage project is a proposed 200.7 MW battery energy storage system located in Cameron County, Texas. The project, developed by Resaca Oasis Storage, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0399, with a queue entry date of December 12, 2024. The proposed commercial operation date is September 20, 2027, and the project's interconnection agreement status is currently in the Facility Study phase.
The point of interconnection for the project is the # 79601 Stillman Substation 138 kV. The development has appeared in recent news coverage regarding energy storage projects in Texas.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cameron
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Resaca Oasis Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
# 79601 Stillman Substation 138 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Resaca Oasis StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.