Calf Creek Storage
100.7 MW storage in Howard, TX · In queue since November 2025 · Proposed COD April 2030
100.7 MW
Capacity
1
Components
Battery
1 year
In Queue
Facility Study
IA Phase
COD target: 2030
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 5m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-04-01
Projected COD moved
2 times
Jul 2028 → Apr 2030
Net change
+21 months
first report to latest
Capacity
101 → 103 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue for Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of September 2029. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing identifies developer as Coyote Ridge Storage, LLC. No news coverage or corporate announcements found to identify a parent operating company or confirm this is a project-specific LLC.
Status: LBNL shows Active status in Facility Study phase with recent queue entry (November 2024). No news coverage exists to provide additional ground-truth validation of project progress.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Calf Creek Storage project is a proposed 103.3 MW hybrid battery energy storage project located in Howard County, Texas. Developed by Coyote Ridge Storage, LLC, the project consists of battery energy storage and other unspecified technologies. It is currently listed as active in the ERCOT interconnection queue under queue ID ERCOT-27INR0325, with an interconnection queue entry date of November 24, 2025, and a proposed commercial operation date of September 20, 2029.
The project intends to interconnect at the Buffalo 138 kV Substation #23837.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Howard
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Coyote Ridge Storage, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Buffalo 138 kV Substation #23837
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Buffalo Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Coyote
Data-driven briefing on Coyote — fleet, generation, financial, and news signals.
Coyote Ridge
Data-driven briefing on Coyote Ridge — fleet, generation, financial, and news signals.
Calf Creek Storage
Data-driven briefing on Calf Creek Storage — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.