Tolivar Power Plant (TEF- Due Diligence)
224.5 MW generation in Reeves, TX · In queue since July 2024 · Proposed COD June 2027
224.5 MW
Capacity
1
Components
Gas
2y 4m
In Queue
IA Executed
IA Phase
Signed Jul 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1 year
IA → COD
1y 11m
Total Duration
1 year
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 24–48 months
Proposed COD: 2027-06-11
Projected COD moved
2 times
Apr 2027 → Jun 2027
Net change
+2 months
first report to latest
Capacity
226 → 225 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with ERCOT
lbnl_queue_snapshotProposed commercial operation date per interconnection filing
lbnl_queue_snapshotResearch sources and reasoning (1 recorded sources)
low confidence at research time
- lbnl_queue_snapshot
Commercial operation date: Only LBNL queue data available with proposed COD of May 2027. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity 'Pecos Power Plant, LLC' is available. No news coverage found to identify parent company or operating entity behind this project-specific LLC.
Status: LBNL shows 'active' status with IA executed as of July 2025, indicating project has secured interconnection agreement and remains in queue.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Tolivar Power Plant (TEF- Due Diligence) is a proposed project located in Reeves County, Texas, within the ERCOT region. Developed by Pecos Power Plant, LLC, the project consists of 225.6 MW of gas-fired generation. It entered the ERCOT interconnection queue as project ERCOT-27INR0297 on July 1, 2024, with a proposed commercial operation date of May 6, 2027.
The project's Interconnection Agreement (IA) has been executed as of November 12, 2024. The point of interconnection (POI) is Tap 138 KV 38045 IH20-38043 COWPEN.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Pecos Power Plant, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 KV 38045 IH20-38043 COWPEN
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Tolivar Power Plant (TEF- Due Diligence)Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.