New Minglewood Energy Center (ERCOT-27INR0255) — Project Summary

Queue ID
ERCOT-27INR0255
Capacity
208.3 MW
Technology
Battery
Status
active
Location
Ward, TX
Region
ERCOT
Developer
Nova Clean Energy LLC
IA Status
Facility Study

New Minglewood Energy Center

ERCOT-27INR0255BetaActiveBatteryERCOTLBNL + Live

208.3 MW storage in Ward, TX · In queue since May 2024 · Proposed COD September 2029

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

208.3 MW

Capacity

1

Components

Battery

2y 6m

In Queue

Facility Study

IA Phase

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 4m

Facilities Study50%
Queue EntryMay 9, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-09-29

Queue history
27INR0255 · 30 monthly ERCOT reports, Apr 2024 – Sep 2026

Projected COD moved

2 times

May 2027 → Sep 2029

Net change

+28 months

first report to latest

Capacity

209 → 208 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 9, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Sep 30, 2027
Differs from queue: Sep 29, 2029From queue filing
Developer in saved assessment
Nova Clean Energy
From queue filing
Status at research time
Active
Active — in Facility Study phase per ERCOT queue, no construction timeline announced publicly
Financing
Not recorded

Milestones in this assessment

IA executedMay 2024Latest in this assessment

Entered ERCOT interconnection queue, Facility Study phase

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of September 2027. No independent news or press releases found to validate or contradict this target date.

Developer: LBNL filing entity is 'Nova Clean Energy LLC'. No press releases or corporate announcements found to determine if this is a project-specific shell LLC or the actual operating company name.

Status: LBNL status shows 'active' with Facility Study underway as of May 2024 queue entry. No public announcements found regarding project progression or milestones.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The New Minglewood Energy Center is a proposed 208.3 MW battery storage project located in Ward County, Texas. Developed by Nova Clean Energy LLC, the project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0255, with a queue entry date of May 9, 2024. The proposed commercial operation date is September 30, 2027.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the #11098 Sand Lake Switch Station (SANDLAKE_5) 345kV. The New Minglewood Energy Center has appeared in recent news coverage regarding energy storage projects in Texas.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Ward

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Nova Clean Energy LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

#11098 Sand Lake Switch Station (SANDLAKE_5) 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.