Maddox Solar
101.3 MW generation in Grayson, TX · In queue since May 2024 · Proposed COD March 2029
101.3 MW
Capacity
1
Components
Solar
2y 6m
In Queue
Facility Study
IA Phase
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-03-01
Projected COD moved
3 times
Jan 2027 → Mar 2029
Net change
+26 months
first report to latest
Capacity
103 → 101 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue and began Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of April 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity 'Industrial Lima Project LLC' is available. No news coverage or corporate announcements found to identify a parent operating company or confirm if this is a project-specific shell entity.
Status: LBNL shows active queue status in Facility Study phase. No news coverage found to provide additional ground-truth on project advancement or delays.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Maddox Solar is a proposed 101.3 MW solar generation project located in Grayson County, Texas. The developer is Industrial Lima Project LLC. The project is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0234, with a queue entry date of May 9, 2024, and a proposed commercial operation date of April 1, 2028. Its interconnection status is currently in the Facility Study phase, and the point of interconnection is Tap 138 kV Haggerty Switch (12677) to Van Al (1754) 138kV.
The Maddox Solar project has been the subject of recent news coverage, with seven articles published across industry, grid, and regulatory categories.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Grayson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Industrial Lima Project LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138 kV Haggerty Switch (12677) to Van Al (1754) 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09
View all articlesForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.