CORRUSCANT BESS (ERCOT-27INR0195) — Project Summary

Queue ID
ERCOT-27INR0195
Capacity
401.45 MW
Technology
Battery
Status
active
Location
Dickens, TX
Region
ERCOT
Developer
AEU Battery Project III LLC
IA Status
Facility Study

CORRUSCANT BESS

ERCOT-27INR0195BetaActiveBatteryERCOTLBNL + Live

401.45 MW storage in Dickens, TX · In queue since February 2024 · Proposed COD April 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

401.45 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 2m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-04-18

Queue history
27INR0195 · 32 monthly ERCOT reports, Feb 2024 – Sep 2026

Projected COD moved

0 times

Apr 2027 → Apr 2027

Net change

0 months

first report to latest

Capacity

337 → 418 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 27, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 18, 2027
From queue filing
Developer in saved assessment
AEU Battery Project III LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue. The September 2026 GIS shows SS completed and FIS started with no IA executed. ercotqueue.com gives a low build-chance score (about 2%). Reported capacity varies by source (401, 418 and 337 MW), and ERCOT spells the name 'CORUSCANT'.
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. ercotqueue.com/project/27INR0195
  2. app.nrgmap.com/queues/ercot-27inr0195
  3. interconnection.fyi/project/ercot-27inr0195

Commercial operation date: The only COD signal is the ERCOT queue date of 2027-04-18. The aggregators (NRG Map: 'Proposed online 2027-04-18'; ercotqueue.com: 'Projected COD Q2 2027') repeat the same ERCOT data. No developer press release or news item gives an independent, financing-backed date.

Developer: Every source lists AEU Battery Project III LLC, and all of them draw on the same ERCOT filing. The name looks like a project SPV, but no source identifies a parent or operating company, so none is asserted.

Status: The ERCOT status data as of 1 Sept 2026 (via NRG Map) shows the project active at the study stage, with no IA and no construction or financing signal. The LBNL status of active is consistent with that.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The proposed CORRUSCANT BESS project is a 337.35 MW battery storage development in Dickens County, Texas. The project, being developed by AEU Battery Project III LLC, is located within the ERCOT region and consists entirely of battery storage.

The project is listed in the ERCOT interconnection queue as entry ERCOT-27INR0195, with a queue entry date of February 27, 2024. Its proposed commercial operation date is April 18, 2027, and its interconnection agreement status is currently in the Facility Study phase. The point of interconnection is Tap 345kV 59904 COTTONWOOD - 60500 EDITHCLA7A.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Dickens

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

AEU Battery Project III LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 59904 COTTONWOOD - 60500 EDITHCLA7A

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Cottonwood Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.