Millsing BESS (ERCOT-27INR0190) — Project Summary

Queue ID
ERCOT-27INR0190
Capacity
501.6 MW
Technology
Battery
Status
active
Location
Grimes, TX
Region
ERCOT
Developer
Millsing BESS
IA Status
Facility Study

Millsing BESS

ERCOT-27INR0190BetaActiveBatteryERCOTLBNL + Live

501.6 MW storage in Grimes, TX · In queue since February 2024 · Proposed COD October 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

501.6 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 8m

Facilities Study50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Completed, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-10-15

Queue history
27INR0190 · 32 monthly ERCOT reports, Feb 2024 – Sep 2026

Projected COD moved

1 time

Jul 2027 → Oct 2028

Net change

+15 months

first report to latest

Capacity

502 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 27, 2024
Facilities study approvedOct 8, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Oct 15, 2028
From queue filing
Developer in saved assessment
—
From queue filing
Status at research time
Active
Active in the ERCOT queue at the Facility Study stage. No IA executed, and no public sign of construction or permitting.
Financing
Not recorded
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. cleanview.co/power-projects/planned/battery-storage-projects/texas/27INR0190/millsing-bess
  2. interconnection.fyi/project/ercot-27inr0190
  3. newsletter.interconnection.fyi/p/interconnection-weekly-project-updates-db7

Commercial operation date: Only queue-derived data exists. Cleanview says 'expected to come online in October 2028', and the interconnection.fyi newsletter shows the proposed completion moved from June 30, 2027 to October 14, 2028. Both appear to mirror the queue filing, not a developer announcement.

Developer: The LBNL developer field repeats the project name, which looks like a project shell entity. No press release or article names a parent or operating company.

Status: LBNL and interconnection.fyi both list the project as active in ERCOT. No search result reports withdrawal, construction, or an executed IA.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Millsing BESS project is a proposed 501.6 MW battery storage project located in Grimes County, Texas. The developer is listed as Millsing BESS. It is currently in the ERCOT interconnection queue as entry ERCOT-27INR0190, with a queue entry date of February 27, 2024, and a proposed commercial operation date of October 15, 2028. The project's interconnection agreement status is currently in the Facility Study phase.

The proposed project consists of 501.6 MW of battery storage capacity. The point of interconnection is the 44645 CNP Singleton 345kV substation. The Millsing BESS project has been mentioned in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Grimes

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Millsing BESS

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

44645 CNP Singleton 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
LMO_ESR_RN
POI Substation
Singleton Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.