Millsing BESS
501.6 MW storage in Grimes, TX · In queue since February 2024 · Proposed COD October 2028
501.6 MW
Capacity
1
Components
Battery
2y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-15
Projected COD moved
1 time
Jul 2027 → Oct 2028
Net change
+15 months
first report to latest
Capacity
502 MW
unchanged in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (3 recorded sources)
low confidence at research time
- cleanview.co/power-projects/planned/battery-storage-projects/texas/27INR0190/millsing-bess
- interconnection.fyi/project/ercot-27inr0190
- newsletter.interconnection.fyi/p/interconnection-weekly-project-updates-db7
Commercial operation date: Only queue-derived data exists. Cleanview says 'expected to come online in October 2028', and the interconnection.fyi newsletter shows the proposed completion moved from June 30, 2027 to October 14, 2028. Both appear to mirror the queue filing, not a developer announcement.
Developer: The LBNL developer field repeats the project name, which looks like a project shell entity. No press release or article names a parent or operating company.
Status: LBNL and interconnection.fyi both list the project as active in ERCOT. No search result reports withdrawal, construction, or an executed IA.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Millsing BESS project is a proposed 501.6 MW battery storage project located in Grimes County, Texas. The developer is listed as Millsing BESS. It is currently in the ERCOT interconnection queue as entry ERCOT-27INR0190, with a queue entry date of February 27, 2024, and a proposed commercial operation date of October 15, 2028. The project's interconnection agreement status is currently in the Facility Study phase.
The proposed project consists of 501.6 MW of battery storage capacity. The point of interconnection is the 44645 CNP Singleton 345kV substation. The Millsing BESS project has been mentioned in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Grimes
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Millsing BESS
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
44645 CNP Singleton 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- LMO_ESR_RN
- POI Substation
- Singleton Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.