Starlight Storage (ERCOT-27INR0107) — Project Summary

Queue ID
ERCOT-27INR0107
Capacity
104.66 MW
Technology
Solar+Battery
Status
active
Location
Mills, TX
Region
ERCOT
Developer
Mills Tx Solar LLC
IA Status
Facility Study

Starlight Storage

ERCOT-27INR0107BetaActiveBatteryBatteryERCOTLBNL + Live

104.66 MW generation in Mills, TX · In queue since February 2024 · Proposed COD May 2030

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

104.66 MW

Capacity

1

Components

Battery

2y 9m

In Queue

Facility Study

IA Phase

Signed Dec 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

1y 10m

IA → COD

4y 5m

Total Duration

1y 10m

Construction50%
Queue EntryFeb 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 31, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2030-05-09

Queue history
27INR0107 · 32 monthly ERCOT reports, Feb 2024 – Sep 2026

Projected COD moved

1 time

Mar 2027 → May 2030

Net change

+38 months

first report to latest

Capacity

105 → 209 MW

changed in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedFeb 27, 2024
Interconnection agreement signedDec 31, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
2030
From queue filing
Developer in saved assessment
Mills Tx Solar LLC
From queue filing
Status at research time
Active
Active — early-stage Facility Study phase, IA target end of 2025
Financing
Not recorded

Milestones in this assessment

IA executedDec 31, 2025Latest in this assessment

Interconnection Agreement target date per ERCOT queue

lbnl_queue_snapshot
Research sources and reasoning (1 recorded sources)

low confidence at research time

  1. lbnl_queue_snapshot

Commercial operation date: Only LBNL queue data available showing proposed COD of May 2030. No independent news or press releases found to validate or update this target date.

Developer: Only LBNL filing entity 'Mills Tx Solar LLC' is available. No press releases or corporate announcements found to identify a parent operating company or confirm if this is a project-specific LLC.

Status: LBNL shows Active status in Facility Study phase with interconnection agreement targeted for December 2025. No contradicting information found in public sources.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Starlight Storage project is a proposed 104.66 MW battery energy storage system located in Mills County, Texas. The project, developed by Mills Tx Solar LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0107, with a queue entry date of February 27, 2024. The proposed commercial operation date is May 9, 2030, and the project's interconnection agreement status is currently in the Facility Study phase.

The Starlight Storage project has been the subject of recent news coverage, with two articles focusing on deals related to the project.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Mills

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Mills Tx Solar LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 138kV 7070 Goldthwaite – 77074 San Saba Switch

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.