Rubicon Power BESS (ERCOT-27INR0096) — Project Summary

Queue ID
ERCOT-27INR0096
Capacity
301.38 MW
Technology
Battery
Status
active
Location
Brazoria, TX
Region
ERCOT
Developer
Rubicon Power LLC
IA Status
Facility Study

Rubicon Power BESS

ERCOT-27INR0096BetaActiveBatteryERCOTLBNL + Live

301.38 MW storage in Brazoria, TX · In queue since November 2023 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

301.38 MW

Capacity

1

Components

Battery

3 years

In Queue

Facility Study

IA Phase

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 1m

Facilities Study50%
Queue EntryNov 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Queue history
27INR0096 · 35 monthly ERCOT reports, Nov 2023 – Sep 2026

Projected COD moved

4 times

Jul 2027 → Dec 2027

Net change

+5 months

first report to latest

Capacity

301 MW

unchanged in the reports

Latest stage

Facilities study done

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedNov 14, 2023
Facilities study approvedAug 23, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Dec 31, 2027
From queue filing
Developer in saved assessment
Rubicon Power LLC
From queue filing
Status at research time
Active
Active in the ERCOT queue at the Facility Study stage with no executed interconnection agreement; no public construction or financing activity found.
Financing
Not recorded
Research sources and reasoning (7 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-27inr0096
  2. ercotqueue.com/project/27INR0096
  3. ercotqueue.com/developer/rubicon-power-llc
  4. cleanview.co/power-projects/planned/battery-storage-projects/texas/27INR0096/rubicon-power-bess
  5. futuregrid.io/interconnections/rubicon-power-bess/
  6. app.nrgmap.com/queues/ercot-27inr0096
  7. txnmenergy.com/~/media/Files/P/PNM-Resources/rates-and-filings/FERC/2024%20TNMP%20FERC%20Form%201.pdf

Commercial operation date: Only the ERCOT/LBNL filing date (proposed COD 2027-12-31) is available. Cleanview's 'Expected online 2027' matches it but appears to be a mirror of the queue data. Futuregrid's 2025-11-15 date looks like an older queue value. No developer press release or financing-backed target was found.

Developer: Every source names Rubicon Power LLC, and ercotqueue.com lists it as a developer with a single project on file. No parent or operating company, press release, or acquisition was found, so the name may itself be a shell entity.

Status: LBNL and NRG Map (active as of 1 Sep 2026) both show the project as active. ercotqueue.com shows no IA and a 1% build chance, and the TNMP FERC Form 1 lists Rubicon Power BESS facility interconnection study activity. Nothing indicates the project has progressed beyond the study stage.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Rubicon Power BESS is a proposed 301.38 MW battery storage project located in Brazoria County, Texas. Developed by Rubicon Power LLC, the project consists entirely of battery storage. It is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0096, with a queue entry date of November 14, 2023.

The proposed commercial operation date for the Rubicon Power BESS project is December 31, 2026. The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 39703 TNMP FM524 138kV location.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Brazoria

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Rubicon Power LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

39703 TNMP FM524 138kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_HOUSTON
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.