Sandow Lakes Energy Station (ERCOT-27INR0071) — Project Summary

Queue ID
ERCOT-27INR0071
Capacity
1291.6 MW
Technology
Gas
Status
active
Location
Milam, TX
Region
ERCOT
Developer
SL Energy Power Plant I, LLC
IA Status
Facility Study

Sandow Lakes Energy Station

ERCOT-27INR0071BetaActiveGasERCOTLBNL + Live

1,291.6 MW generation in Milam, TX · In queue since March 2024 · Proposed COD April 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

1,291.6 MW

Capacity

1

Components

Gas

2y 8m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 1m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-04-01

Queue history
27INR0071 · 21 monthly ERCOT reports, Jan 2025 – Sep 2026

Projected COD moved

1 time

Mar 2028 → Apr 2028

Net change

+1 months

first report to latest

Capacity

1264 → 1292 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 22, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Apr 1, 2028
From queue filing
Developer in saved assessment
Sandow Lakes Energy Co.
Filed as SL Energy Power Plant I, LLC
Status at research time
Active
Active, in Facility Study. $450M Macquarie debt financing (Oct 2025) is funding long-lead equipment, including two Siemens Energy SGT6-9000HL turbines. No construction start has been confirmed.
Financing
Secured
$450M debt commitment from Macquarie Asset Management, reported 2025-10-30, to secure long-lead equipment. This appears to be an initial tranche rather than full project financing.

Milestones in this assessment

Financing closeOct 30, 2025

Macquarie commits $450M in debt financing for the Sandow Lakes CCGT, enabling long-lead equipment procurement.

gastopowerjournal.com
COD target2028Latest in this assessment

Developer targets start of operations by 2028 for the 1.2 GW plant with two Siemens Energy SGT6-9000HL turbines.

constructionreviewonline.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. gastopowerjournal.com/news/projectsandfinance/macquarie-commits-450m-for-sandow-lakes-ccgt-in-texas/
  2. realassets.ipe.com/news/macquarie-provides-450m-for-12gw-gas-turbine-project-in-texas/10133377.article
  3. constructionreviewonline.com/gas-fired-power-plant-scheduled-to-be-built-in-lee-county-texas/
  4. powermag.com/new-1-2-gw-natural-gas-fired-plant-announced-for-texas/
  5. cleanview.co/power-projects/planned/natural-gas-power-plants/texas/27INR0071/sandow-lakes-energy-station

Commercial operation date: The LBNL proposed COD is 2028-04-01. The developer's announcement, as recapped by Construction Review (Mar 2026), says the plant is 'scheduled to begin operations by 2028', and Cleanview also lists 'Expected online 2028'. The year matches, and the specific date comes only from LBNL.

Developer: LBNL files the project under the project LLC 'SL Energy Power Plant I, LLC'. The press release (via POWER and Construction Review) names Sandow Lakes Energy Co. as the company building the plant on land it owns. Macquarie appears only as a lender, so there is no ownership change.

Status: LBNL shows the project as active in the Facility Study stage, and no source reports withdrawal or suspension. The 2025 financing and the 2026 coverage show the project is still advancing.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Sandow Lakes Energy Station is a proposed 1264.34 MW gas-fired generation project located in Milam County, Texas. Developed by SL Energy Power Plant I, LLC, the project is interconnected within the ERCOT region under queue ID ERCOT-27INR0071. The project entered the ERCOT interconnection queue on March 22, 2024, with a proposed commercial operation date of April 1, 2028. Its interconnection status is currently in the Facility Study phase.

The proposed project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Milam

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

SL Energy Power Plant I, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

#13430 Sandow Switch 138kV

Data Source

LBNL + Live

TransactionDebt financingGas to Power Journal · 2025-10-30
Deal value$450.0MGas to Power Journal · 2025-10-30
LenderMacquarie Asset ManagementGas to Power Journal · 2025-10-30
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (2)Beta

Last updated 2026-03-26

View all articles