Darkwood Solar
150.76 MW hybrid in Comanche, TX · In queue since June 2023 · Proposed COD September 2027
150.76 MW
Capacity
1
Components
Solar
3y 5m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Completed, IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-09-20
Projected COD moved
1 time
Jan 2027 → Sep 2027
Net change
+8 months
first report to latest
Capacity
150 → 152 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
ONCOR interconnection filings for Darkwood Solar & Darkwood BESS with Texas PUC
interchange.puc.texas.govExpected online September 2027 per multiple tracking sources
cleanview.coResearch sources and reasoning (5 recorded sources)
high confidence at research time
- cleanview.co/planned-solar-projects/TX/68478_DRK/darkwood-solar
- facebook.com/groups/erathcountystopsolarfarmshere/posts/1636489723727376/
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- bloximages.newyork1.vip.townnews.com/thecomanchechief.com/content/tncms/assets/v3/editorial/d/23/d23c6420-675b-4875-94e0-a6f72b7eca85/6802814d32c41.pdf.pdf
- eia.gov/electricity/monthly/epm_table_grapher.php?t=epmt_6_05
Commercial operation date: LBNL queue date of 2027-09-20 is confirmed by multiple independent sources including Cleanview (September 2027), EIA database (2027-10), and local PDF document (01/30/2027 completion date). No contradictory signals found.
Developer: LBNL filing entity is 'Mustang Creek Solar, LLC' (project LLC). Facebook community post explicitly identifies the parent structure: 'Mustang Solar LLC for Core Solar, parent company TotalEnergies.' This is a typical shell-LLC arrangement.
Status: LBNL status 'active' at Facility Study stage is confirmed by Texas PUC Interchange filings showing active regulatory proceedings with ONCOR as recently as November 2025. No withdrawal or suspension signals.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Darkwood Solar project is a proposed 150.76 MW solar generation facility in Comanche County, Texas. Developed by Mustang Creek Solar, LLC, the project consists of 150.76 MW of solar photovoltaic generation. It is listed in the ERCOT interconnection queue as entry ERCOT-27INR0049, with a queue entry date of June 28, 2023, and a proposed commercial operation date of September 20, 2027. The project's interconnection status is currently in the Facility Study phase.
The proposed project is linked to the existing Darkwood Solar operating plant (EIA ID 68478). Recent news coverage has discussed the development.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Comanche
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mustang Creek Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345KV 1900 Comanche Peak to 1440 Comanche SS
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- POI Substation
- Proctor Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.