Short Creek BESS (ERCOT-27INR0029) — Project Summary

Queue ID
ERCOT-27INR0029
Capacity
155.66 MW
Technology
Solar+Battery
Status
active
Location
Wichita, TX
Region
ERCOT
Developer
Wichita Solar I, LLC
IA Status
Facility Study

Short Creek BESS

ERCOT-27INR0029BetaActiveBatteryBatteryERCOTLBNL + Live

155.66 MW generation in Wichita, TX · In queue since April 2023 · Proposed COD July 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

155.66 MW

Capacity

1

Components

Battery

3y 7m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

5y 3m

Facilities Study50%
Queue EntryApr 19, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-01

Queue history
27INR0029 · 42 monthly ERCOT reports, Apr 2023 – Sep 2026

Projected COD moved

2 times

Dec 2027 → Jul 2028

Net change

+7 months

first report to latest

Capacity

152 → 156 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedApr 19, 2023

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Jul 1, 2028
From queue filing
Developer in saved assessment
Wichita Solar I, LLC
From queue filing
Status at research time
Active
Active — in Facility Study phase per LBNL queue, no construction or financing announcements found
Financing
Not recorded

Milestones in this assessment

IA executedApr 19, 2023Latest in this assessment

Queue request submitted to ERCOT, entered Facility Study phase

renewablesinfo.org
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. renewablesinfo.org/project/ercot-27inr0029-short-creek-bess
  2. modo-content-service-prod.s3.amazonaws.com/media/reports/2024/05/22/ERCOT_BESS_buildout_report_May_2024_YwMZT0X.xlsx
  3. interconnection.fyi/projects/state/TX

Commercial operation date: Only LBNL queue snapshot provides a COD target of July 2028. No news articles or press releases mention specific commissioning dates for Short Creek BESS, so LBNL remains the sole source.

Developer: All sources consistently identify 'Wichita Solar I, LLC' as the developer. No parent company or operating entity is mentioned in any search results, suggesting this may be the actual operating entity rather than a shell LLC.

Status: LBNL reports 'active' status with Facility Study in progress. No news coverage indicates construction activity, financing close, or status changes. Project appears to be in early interconnection study phase.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Short Creek BESS project is a proposed 150.51 MW battery storage project located in Wichita County, Texas. The developer is Wichita Solar I, LLC. It is interconnected within the ERCOT region under queue ID ERCOT-27INR0029, with an interconnection queue entry date of April 19, 2023. The proposed commercial operation date is July 1, 2028, and the project's interconnection agreement status is currently in the Facility Study phase.

The project consists of 150.51 MW of battery storage capacity. The point of interconnection is at the Tap 345kV 6101 Riley - 1425 Fisher Road Switch. The Short Creek BESS project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Wichita

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Wichita Solar I, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 6101 Riley - 1425 Fisher Road Switch Ckt 1

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.