Felix West Solar
200.95 MW hybrid in Wilbarger, TX · In queue since January 2023 · Proposed COD December 2028
200.95 MW
Capacity
1
Components
Solar
3y 10m
In Queue
IA Executed
IA Phase
Signed Feb 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 1m
IA → COD
3y 10m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 18–30 months
Proposed COD: 2028-12-31
Projected COD moved
1 time
Jul 2027 → Dec 2028
Net change
+17 months
first report to latest
Capacity
201 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.
Milestones in this assessment
Expected online date per ERCOT capacity planning documents
ercot.comResearch sources and reasoning (5 recorded sources)
medium confidence at research time
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
- ercot.com/files/docs/2025/11/06/Capacity-Changes-by-Fuel-Type-Charts_October_2025.xlsx
- ercot.com/files/docs/2025/12/05/MORA_February2026.pdf
- ercotqueue.com/developer/felix-1-llc
- cleanview.co/planned-solar-projects/TX/27INR0012/felix-west-solar
Commercial operation date: LBNL shows 2028-12-31, but ERCOT's November 2025 Solar Chart and February 2026 MORA both list 2027 as the expected online date. The IA was executed Feb 2025, making 2027 more realistic than the original 2028 filing.
Developer: All sources consistently identify Felix 1, LLC as the developer with no evidence of a parent company or operating entity. No press releases, acquisitions, or corporate announcements found.
Status: LBNL status 'active' with IA executed 2025-02-21 is confirmed. Project appears in ERCOT's current planning documents as an active 2027 project.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Felix West Solar project is a proposed 200.95 MW solar generation facility located in Wilbarger County, Texas. The project, developed by Felix 1, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0012, with a queue entry date of January 17, 2023. The proposed commercial operation date is December 31, 2028.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 6101 Riley 345 kV substation. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wilbarger
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Felix 1, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6101 Riley 345 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- ELECTRAW_1_2
- POI Substation
- Riley Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.