Felix West Solar (ERCOT-27INR0012) — Project Summary

Queue ID
ERCOT-27INR0012
Capacity
200.95 MW
Technology
Solar+Battery
Status
active
Location
Wilbarger, TX
Region
ERCOT
Developer
Felix 1, LLC
IA Status
IA Executed

Felix West Solar

ERCOT-27INR0012BetaActiveSolarBatteryERCOTLBNL + Live

200.95 MW hybrid in Wilbarger, TX · In queue since January 2023 · Proposed COD December 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

200.95 MW

Capacity

1

Components

Solar

3y 10m

In Queue

IA Executed

IA Phase

Signed Feb 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

2y 1m

IA → COD

3y 10m

Total Duration

2y 1m

Construction75%
Queue EntryJan 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 21, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2028-12-31

Queue history
27INR0012 · 45 monthly ERCOT reports, Jan 2023 – Sep 2026

Projected COD moved

1 time

Jul 2027 → Dec 2028

Net change

+17 months

first report to latest

Capacity

201 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedJan 17, 2023
Interconnection agreement signedFeb 21, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
2027
Differs from queue: Dec 31, 2028
Developer in saved assessment
Felix 1, LLC
From queue filing
Status at research time
Active
Active — IA executed February 2025, FIS (Facility Interconnection Study) pending per ercotqueue.com
Financing
Not recorded

Milestones in this assessment

IA executedFeb 21, 2025

Interconnection Agreement executed with ERCOT

interconnectionfyi.substack.com
COD target2027Latest in this assessment

Expected online date per ERCOT capacity planning documents

ercot.com
Research sources and reasoning (5 recorded sources)

medium confidence at research time

  1. interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-602
  2. ercot.com/files/docs/2025/11/06/Capacity-Changes-by-Fuel-Type-Charts_October_2025.xlsx
  3. ercot.com/files/docs/2025/12/05/MORA_February2026.pdf
  4. ercotqueue.com/developer/felix-1-llc
  5. cleanview.co/planned-solar-projects/TX/27INR0012/felix-west-solar

Commercial operation date: LBNL shows 2028-12-31, but ERCOT's November 2025 Solar Chart and February 2026 MORA both list 2027 as the expected online date. The IA was executed Feb 2025, making 2027 more realistic than the original 2028 filing.

Developer: All sources consistently identify Felix 1, LLC as the developer with no evidence of a parent company or operating entity. No press releases, acquisitions, or corporate announcements found.

Status: LBNL status 'active' with IA executed 2025-02-21 is confirmed. Project appears in ERCOT's current planning documents as an active 2027 project.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Felix West Solar project is a proposed 200.95 MW solar generation facility located in Wilbarger County, Texas. The project, developed by Felix 1, LLC, is currently active in the ERCOT interconnection queue as entry ERCOT-27INR0012, with a queue entry date of January 17, 2023. The proposed commercial operation date is December 31, 2028.

The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the 6101 Riley 345 kV substation. The project has appeared in recent news.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Wilbarger

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Felix 1, LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

6101 Riley 345 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
Nearest Node (Estimated)
ELECTRAW_1_2
POI Substation
Riley Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.