Meadow Park BESS
9.95 MW storage in Tarrant, TX · In queue since June 2025 · Proposed COD February 2026
9.95 MW
Capacity
1
Components
Battery
1y 5m
In Queue
IA Executed
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8 months
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-02-10
Projected COD moved
1 time
Jan 2026 → Feb 2026
Net change
+1 months
first report to latest
Capacity
10 MW
unchanged in the reports
Latest stage
Commercial operation
last listed Mar 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Meadow Park BESS is a proposed battery energy storage development project in Tarrant County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by Meadow Park ESS Assets, LLC, the standalone storage project has a total capacity of 9.95 MW. It would interconnect at the Meadow Park substation, an Oncor facility (station code MDWPK) operating at 138 kV, through transformer number 2. The corresponding ERCOT bus is MEADPRK1_8 (bus number 2039).
The project entered the ERCOT interconnection queue on June 19, 2025, under queue ID 26INR0699, and its status is active. An interconnection agreement has been executed, and the proposed commercial operation date is February 10, 2026. The project is linked with high confidence to the Meadow Park Energy Center (EIA plant ID 69234), an existing plant record in U.S. Energy Information Administration data.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Mar 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Tarrant
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Meadow Park ESS Assets, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name: Meadow Park | Oncor 5-digit code: MDWPK | Oncor XFMR Number: 2 | ERCOT Bus Name: MEADPRK1_8 | ERCOT Bus#: 2039 | ERCOT Load Name: LDLXFMR2 | Substation Transmission kV: 138 kV | ERCOT Node#: CN1
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- HIGH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Meadow Park BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.