Staghorn Gas
9.99 MW generation in Ward, TX · In queue since May 2025 · Proposed COD May 2026
9.99 MW
Capacity
1
Components
Gas
1y 6m
In Queue
IA Executed
IA Phase
Signed May 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
<1 month
IA → COD
1 year
Total Duration
<1 month
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2026-05-02
Projected COD moved
1 time
May 2026 → Oct 2026
Net change
+5 months
first report to latest
Capacity
10 MW
unchanged in the reports
Latest stage
Synchronized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Staghorn Gas is a proposed natural gas-fired generation project located in Ward County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by RPC Merchant LLC, the project has a total planned capacity of 9.99 MW, consisting entirely of gas-fired generation. The project's point of interconnection is the Staghorn station, connecting at 138 kV transmission voltage via the TNMP transformer T3 (load name STGHRN_3, bus number 37990, node 9984).
The project is listed in the ERCOT interconnection queue under queue ID ERCOT-26INR0698 and holds an active status. It entered the queue on May 29, 2025, and executed its interconnection agreement the following day, on May 30, 2025. The proposed commercial operation date is May 2, 2026. Staghorn Gas has been linked to an existing operating plant in U.S. Energy Information Administration (EIA) records, also named Staghorn Gas (EIA plant ID 69271), with a match confidence of 0.88.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ward
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
RPC Merchant LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
STATION NAME: STAGHORN LOAD NAME: STGHRN_3 TNMP TRANSFORMER NAME: T3 BUS #: 37990 TRANSMISSION VOLTAGE: 138KV NODE: 9984
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SWOOSE1_U1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.