Exergy Energy West Texas Natural Gas Reciprocating Power I
400 MW generation in Reeves, TX · In queue since July 2025 · Proposed COD May 2027
400 MW
Capacity
1
Components
Gas
1y 4m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
1y 10m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-05-01
Projected COD moved
0 times
May 2027 → May 2027
Net change
0 months
first report to latest
Capacity
400 MW
unchanged in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- energychoicematters.com/stories/20250801b.html
- exergyenergy.com/westtexas/
- exergyenergy.com/wp-content/uploads/2025/08/Power-Plant-Information.pdf
- ercotqueue.com/project/26INR0685
- bizapedia.com/tx/exergy-energy-west-texas-natural-gas-reciprocating-power-llc.html
Commercial operation date: LBNL proposed COD is 2027-05-01. The developer's FERC filing, reported Aug 2025, estimates generation in Q3 2026, and its website promises interconnection 'by end of year 2026'. That gap is under a year, and the project is still at Facility Study with no IA, so I kept the LBNL date. The earlier developer target looks aggressive.
Developer: The project name, the 400 MW gas reciprocating engines and the Reeves County location match Exergy Energy's 'Exergy Energy Pecos Power' PGC registration, so the operating company is Exergy Energy. No source explicitly ties August Partners LLC to Exergy, so I infer it is the queue-filing entity.
Status: LBNL and the ERCOT queue trackers show the project as active with no IA (ercotqueue.com lists a 9% build chance). I found no evidence of withdrawal or of construction.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Exergy Energy West Texas Natural Gas Reciprocating Power I project is a proposed 400 MW natural gas-fired generation project located in Reeves County, Texas. Developed by August Partners LLC, the project consists of internal combustion technology. It is currently active in the ERCOT interconnection queue as entry ERCOT-26INR0685, with a queue entry date of July 22, 2025.
The proposed commercial operation date for the Exergy Energy West Texas Natural Gas Reciprocating Power I project is May 1, 2027. The point of interconnection is the 38095 TNJACKRBT1 138kV substation. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Reeves
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
August Partners LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
38095 TNJACKRBT1 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
TOCE TX BESS 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Texas energy overview
Summary analysis with parallel narrative sections and visualizations.
State-by-state breakdown for ERCOT (Texas)
Summary analysis with parallel narrative sections and visualizations.
Queue projects in Texas
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.