Lyra Storage (ERCOT-26INR0636) — Project Summary

Queue ID
ERCOT-26INR0636
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Borden, TX
Region
ERCOT
Developer
JUNO BESS I
IA Status
IA Executed

Lyra Storage

ERCOT-26INR0636BetaActiveBatteryBatteryERCOTLBNL + Live

500 MW generation in Borden, TX · In queue since May 2025 · Proposed COD November 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

500 MW

Capacity

1

Components

Battery

1y 6m

In Queue

IA Executed

IA Phase

Signed Aug 2025

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3 months

IA → COD

1y 3m

Total Duration

3 months

Schedule

0 months past proposed COD

Construction75%
Queue EntryMay 27, 2025

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 13, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

SS Completed, FIS Started, IA

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2026-11-12

Queue history
26INR0636 · 17 monthly ERCOT reports, May 2025 – Sep 2026

Projected COD moved

0 times

Nov 2026 → Nov 2026

Net change

0 months

first report to latest

Capacity

500 MW

unchanged in the reports

Latest stage

IA signed

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMay 27, 2025
Interconnection agreement signedAug 13, 2025

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Nov 12, 2026
From queue filing
Developer in saved assessment
JUNO BESS I
From queue filing
Status at research time
IA Executed
Active in the ERCOT queue with an executed IA (Aug 2025). Paired with the Lyra Solar project at the 345kV Muleshoe substation. No construction start has been reported, and ercotqueue.com notes FIS pending.
Financing
Secured
Groundtrace lists Lyra Storage as '(financed)', but gives no amount, lender, or date. This is a single aggregator tag, not corroborated by a press release.

Milestones in this assessment

IA executedAug 13, 2025Latest in this assessment

Interconnection agreement signed for Lyra Storage at 345kV Muleshoe (#59922), per LBNL and Quicksand Check.

quicksandcheck.com
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. interconnection.fyi/project/ercot-26inr0636
  2. quicksandcheck.com/texas/borden-county/
  3. groundtrace.io/developers/juno-bess-i-7fhqdybjwdtmy
  4. ercotqueue.com/project/26INR0636
  5. cleanview.co/power-projects/planned/battery-storage-projects/texas/26INR0636/lyra-storage

Commercial operation date: Only queue-derived data supports the date. Aggregators (interconnection.fyi, Quicksand Check) repeat the LBNL/ERCOT proposed COD of Nov 2026, and Cleanview says 'Expected online 2026'. No developer press release or news gives an independent target.

Developer: All sources name JUNO BESS I, which looks like a project-level entity. No parent or operating company was identified. The sister project Lyra Solar is listed under 'Juno Solar 4', which suggests a 'Juno' family of entities, but the parent is not named.

Status: LBNL shows an executed IA dated 2025-08-13, and Quicksand Check confirms 'Signed Aug 2025'. Groundtrace states none of the developer's projects is under construction yet.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Lyra Storage project is a proposed 500 MW hybrid battery energy storage system located in Borden County, Texas. Developed by JUNO BESS I, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue (ERCOT-26INR0636) on May 27, 2025. An Interconnection Agreement (IA) was executed on August 13, 2025. The proposed commercial operation date is November 12, 2026, with a point of interconnection at the 345kV MULESHOE substation.

The Lyra Storage project is currently listed as active in the ERCOT interconnection queue. The project utilizes battery energy storage technology, with "Other" specified as an additional technology detail.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Borden

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

JUNO BESS I

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

345kV MULESHOE (#59922)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_WEST
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.