Tennuto BESS
202 MW storage in Cooke, TX · In queue since January 2025 · Proposed COD December 2027
202 MW
Capacity
1
Components
Battery
1y 6m
In Queue
Facility Study
IA Phase
COD target: 2027
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Project entered ERCOT queue on 2025-01-28 at Facility Study phase
The Tennuto BESS project is a proposed 202 MW hybrid battery energy storage system located in Cooke County, Texas. Developed by Tennuto BESS, LLC, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue (ERCOT-26INR0598) on January 28, 2025. The proposed commercial operation date is December 31, 2027.
The project, which is currently listed as active in the queue, consists of battery energy storage paired with another unspecified technology. The point of interconnection is at Wolfridge (#730). The Tennuto BESS project has appeared in recent news coverage regarding energy storage development in Texas.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cooke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tennuto BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Wolfridge (#730)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.