Tennuto BESS
202 MW storage in Cooke, TX · In queue since January 2025 · Proposed COD December 2027
202 MW
Capacity
1
Components
Battery
1y 10m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
Projected COD moved
1 time
May 2027 → Dec 2027
Net change
+7 months
first report to latest
Capacity
202 MW
unchanged in the reports
Latest stage
Cancelled
last listed Jun 2026
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Project entered ERCOT queue on 2025-01-28 at Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2027-12-31. No independent news or press releases found to validate or contradict this date.
Developer: Only LBNL filing entity 'Tennuto BESS, LLC' is available. No news coverage or corporate announcements found to identify a parent operating company or confirm this is a project-specific LLC.
Status: LBNL status shows 'active' with Facility Study phase. No public announcements or news coverage found to provide additional ground-truth status updates.
About
Generated Apr 10, 2026 · Predates Jun 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Tennuto BESS project is a proposed 202 MW hybrid battery energy storage system located in Cooke County, Texas. Developed by Tennuto BESS, LLC, the project is interconnected within the ERCOT region and entered the ERCOT interconnection queue (ERCOT-26INR0598) on January 28, 2025. The proposed commercial operation date is December 31, 2027.
The project, which is currently listed as active in the queue, consists of battery energy storage paired with another unspecified technology. The point of interconnection is at Wolfridge (#730). The Tennuto BESS project has appeared in recent news coverage regarding energy storage development in Texas.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Jun 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Cooke
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Tennuto BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Wolfridge (#730)
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.