Apple BESS
9.9 MW storage in Ector, TX · Proposed COD May 2026
9.9 MW
Capacity
1
Components
Battery
—
In Queue
IA Executed
IA Phase
Signed Apr 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
IA → COD
1y 1m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2026-05-05
Projected COD moved
3 times
Mar 2026 → Nov 2026
Net change
+8 months
first report to latest
Capacity
10 MW
unchanged in the reports
Latest stage
Energized
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Apple BESS is a proposed battery energy storage development project located in Ector County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. Developed by Apple Infra LLC, the standalone storage project has a total capacity of 9.9 MW, consisting entirely of a single battery component. The project is identified in the ERCOT interconnection queue as ERCOT-26INR0574 and currently holds an active status.
The project has an executed interconnection agreement (IA), signed on April 3, 2025, and has a proposed commercial operation date of May 5, 2026. Its point of interconnection is the Apple station, which carries the Oncor code APPLE and connects through Oncor transformer #1 at a substation transmission voltage of 138 kV. In ERCOT's system, the connection point is designated bus APPLE_9 (bus #1276), with the associated load name LDLXFMR1. The project is linked to an existing plant record in U.S. Energy Information Administration (EIA) data, matched to the EIA plant "Apple BESS" (plant ID 69318) with a match confidence of 0.87.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Ector
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Apple Infra LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Station Name - Apple Oncor 5-digit code - APPLE Oncor XFMR # - 1 ERCOT Bus Name - APPLE_9 ERCOT Bus # 1276 EROCT Load Name - LDLXFMR1 Substation Transmission kV - 138
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- HIGH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.