Longview Wind
352.6 MW generation in Dawson, TX · In queue since September 2025 · Proposed COD December 2028
352.6 MW
Capacity
1
Components
Wind
10 months
In Queue
IA Executed
IA Phase
Signed Dec 2025
Queue → IA
3 months
IA → COD
3 years
Total Duration
3 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2028-12-01
Interconnection Agreement executed per LBNL queue data
Longview Wind, a proposed wind generation project in Dawson County, Texas, is being developed by Longview Wind, LLC. The project, with a total capacity of 352.6 MW, is listed in the ERCOT interconnection queue as entry ERCOT-26INR0530, with a queue entry date of September 22, 2025. An Interconnection Agreement (IA) was executed on December 16, 2025. The proposed commercial operation date (COD) is December 1, 2028.
The project will interconnect at the Venturi substation (Bus #59923). The Longview Wind project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Dawson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Longview Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Venturi (Bus #59923)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.