Electric E - West Texas Generation
43.64 MW generation in Loving, TX · In queue since October 2024 · Proposed COD April 2028
43.64 MW
Capacity
1
Components
Gas
1y 9m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-09
Electric E - West Texas Generation is a proposed 44.4 MW natural gas generation project located in Loving County, Texas. The project, developed by Electric E Power Marketing, entered the ERCOT interconnection queue as entry ERCOT-26INR0529 on October 18, 2024. It is currently undergoing a Facility Study, with a proposed commercial operation date of April 9, 2028.
The project consists of 44.4 MW of gas-fired generation. Its point of interconnection is #11166 ENPOD 138kV. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Loving
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Electric E Power Marketing
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#11166 ENPOD 138kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Electric E - West Texas GenerationForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.