Mandolin Storage SLF
— hybrid in Starr, TX · In queue since July 2024 · Proposed COD June 2029
—
Capacity
0
Components
2y 3m
In Queue
—
IA Status
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-15
Mandolin Storage SLF (queue ID ERCOT-26INR0528) is a proposed battery energy storage development project in Starr County, Texas, within the Electric Reliability Council of Texas (ERCOT) region. The project is being developed by Mandolin Energy Center I, LLC. It is classified as a hybrid project, with technology components listed as battery energy storage and an additional component categorized as "Other." Total capacity and individual component capacities are not specified in the available queue data.
The project entered the ERCOT interconnection queue on July 22, 2024, and its queue status is active. Its proposed commercial operation date is June 15, 2029. The planned point of interconnection is a tap on the 345 kV transmission line between the Del Sol (bus 80355) and Rapido (bus 80227) substations. The status of an interconnection agreement for the project is not indicated in the available data.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Starr
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Mandolin Energy Center I, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 80355 Del Sol - 80227 Rapido
Data Source
Live · ERCOT
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_WEST
- Hub Confidence
- MEDIUM
- POI Substation
- Mesa del Sol Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Mandolin Storage SLFForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.