Prospector Energy Storage (ERCOT-26INR0485) — Project Summary

Queue ID
ERCOT-26INR0485
Capacity
204.6 MW
Technology
Battery
Status
active
Location
Howard, TX
Region
ERCOT
Developer
Prospector Storage LLC
IA Status
Facility Study

Prospector Energy Storage

ERCOT-26INR0485BetaActiveBatteryERCOTLBNL + Live

204.6 MW storage in Howard, TX · In queue since August 2024 · Proposed COD September 2026

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

204.6 MW

Capacity

1

Components

Battery

2y 3m

In Queue

Facility Study

IA Phase

COD target: 2026

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

2y 1m

Schedule

2 months past proposed COD

Facilities Study50%
Queue EntryAug 16, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-09-30

Queue history
26INR0485 · 28 monthly ERCOT reports, Jun 2024 – Sep 2026

Projected COD moved

0 times

Sep 2026 → Sep 2026

Net change

0 months

first report to latest

Capacity

201 → 205 MW

changed in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedAug 16, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.

Research COD
Sep 30, 2026
From queue filing
Developer in saved assessment
Prospector Storage LLC
From queue filing
Status at research time
Active
Active — Facility Study phase, no interconnection agreement yet. Third-party analysis suggests 5% build probability.
Financing
Not recorded

Milestones in this assessment

IA executedLatest in this assessment

No interconnection agreement executed; project in Facility Study phase

ercotqueue.com
Research sources and reasoning (3 recorded sources)

low confidence at research time

  1. ercotqueue.com/project/26INR0485
  2. interconnection.fyi/project/ercot-26inr0485
  3. ercotqueue.com/developer/prospector-storage-llc

Commercial operation date: Only LBNL queue data provides a COD of September 30, 2026. No independent news sources or press releases found to validate or update this target date.

Developer: All sources consistently identify Prospector Storage LLC as the developer. No parent company or operating entity identified in available sources, suggesting this may be the actual operating entity rather than a shell LLC.

Status: LBNL shows 'active' status in Facility Study phase with no IA executed. Queue tracking sites note 'No IA' status and assign low build probability based on early interconnection stage.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Prospector Energy Storage is a proposed 204.6 MW battery storage project located in Howard County, Texas. The project, developed by Prospector Storage LLC, is interconnected within the ERCOT region under queue ID ERCOT-26INR0485. It entered the interconnection queue on August 16, 2024, and has a proposed commercial operation date of September 30, 2026. The project's interconnection status is currently in the Facility Study phase.

The Prospector Energy Storage project consists of 204.6 MW of battery storage capacity. The project has been the subject of recent news coverage, with three articles categorized under the industry sector.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Howard

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Prospector Storage LLC

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Natural Dam 138kV Substation (23836)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_SOUTH
Hub Confidence
MEDIUM
POI Substation
Sam Dam Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.