Prospector Energy Storage
204.6 MW storage in Howard, TX · In queue since August 2024 · Proposed COD September 2026
204.6 MW
Capacity
1
Components
Battery
2y 3m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2y 1m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
Projected COD moved
0 times
Sep 2026 → Sep 2026
Net change
0 months
first report to latest
Capacity
201 → 205 MW
changed in the reports
Latest stage
Screening started
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
No interconnection agreement executed; project in Facility Study phase
ercotqueue.comResearch sources and reasoning (3 recorded sources)
low confidence at research time
- ercotqueue.com/project/26INR0485
- interconnection.fyi/project/ercot-26inr0485
- ercotqueue.com/developer/prospector-storage-llc
Commercial operation date: Only LBNL queue data provides a COD of September 30, 2026. No independent news sources or press releases found to validate or update this target date.
Developer: All sources consistently identify Prospector Storage LLC as the developer. No parent company or operating entity identified in available sources, suggesting this may be the actual operating entity rather than a shell LLC.
Status: LBNL shows 'active' status in Facility Study phase with no IA executed. Queue tracking sites note 'No IA' status and assign low build probability based on early interconnection stage.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Prospector Energy Storage is a proposed 204.6 MW battery storage project located in Howard County, Texas. The project, developed by Prospector Storage LLC, is interconnected within the ERCOT region under queue ID ERCOT-26INR0485. It entered the interconnection queue on August 16, 2024, and has a proposed commercial operation date of September 30, 2026. The project's interconnection status is currently in the Facility Study phase.
The Prospector Energy Storage project consists of 204.6 MW of battery storage capacity. The project has been the subject of recent news coverage, with three articles categorized under the industry sector.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Howard
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Prospector Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Natural Dam 138kV Substation (23836)
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- MEDIUM
- POI Substation
- Sam Dam Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Prospector Energy Storage
Data-driven briefing on Prospector Energy Storage — fleet, generation, financial, and news signals.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.