Sorghum BESS (ERCOT-26INR0474) — Project Summary

Queue ID
ERCOT-26INR0474
Capacity
208.9 MW
Technology
Battery
Status
active
Location
Wharton, TX
Region
ERCOT
Developer
Blue Creek BESS, LLC
IA Status
IA Executed

Sorghum BESS

ERCOT-26INR0474BetaActiveBatteryERCOTLBNL + Live

208.9 MW storage in Wharton, TX · In queue since April 2024 · Proposed COD December 2027

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

208.9 MW

Capacity

1

Components

Battery

2y 3m

In Queue

IA Executed

IA Phase

Signed Jan 2025

Interconnection

Queue → IA

9 months

IA → COD

2y 11m

Total Duration

9 months

Construction75%
Queue EntryApr 15, 2024

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJan 8, 2025

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2027-12-01

Cross-source intelligence
Beta
Medium confidence·4 sources·as of 2026-06-01
Expected COD
2027-12-01
From queue filing
Developer
Blue Creek BESS, LLC
From queue filing
Status
IA Executed
IA Executed — Interconnection Agreement signed January 8, 2025 with CenterPoint Energy Houston Electric per Texas PUC filing 35077. Project active in ERCOT queue.
Financing
Unannounced
Key milestones
IA executedJan 8, 2025

ERCOT Standard Generation Interconnection Agreement executed with CenterPoint Energy Houston Electric

source
COD targetDec 1, 2027Most recent

Proposed commercial operation date per ERCOT queue

source
About

The proposed Sorghum BESS project is a 208.9 MW battery storage development in Wharton County, Texas. Developed by Blue Creek BESS, LLC, the project entered the ERCOT interconnection queue as ERCOT-26INR0474 on April 15, 2024. The current proposed commercial operation date is December 1, 2027, and the interconnection agreement has been executed.

The project consists solely of battery storage with a total capacity of 208.9 MW. The point of interconnection is the #44060 Blue Substation at 345kV. The project is currently listed as active within the ERCOT queue. Recent news coverage has discussed the project.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

TX

County

Wharton

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

Blue Creek BESS, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

#44060 Blue Substation 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
LOW

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.

No Ask reports yet for this entity.

Ask about Sorghum BESS
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.