Sorghum BESS
208.9 MW storage in Wharton, TX · In queue since April 2024 · Proposed COD December 2027
208.9 MW
Capacity
1
Components
Battery
2y 7m
In Queue
IA Executed
IA Phase
Signed Jan 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
9 months
IA → COD
2y 11m
Total Duration
9 months
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Completed, IA
Project under construction
Typical: 6–18 months
Proposed COD: 2027-12-01
Projected COD moved
1 time
Dec 2026 → Dec 2027
Net change
+12 months
first report to latest
Capacity
209 MW
unchanged in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
ERCOT Standard Generation Interconnection Agreement executed with CenterPoint Energy Houston Electric
interchange.puc.texas.govProposed commercial operation date per ERCOT queue
interconnection.fyiResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- interconnection.fyi/project/ercot-26inr0474
- interchange.puc.texas.gov/search/filings/?UtilityType=A&ControlNumber=35077&FilingParty=centerpoint&DocumentType=ALL&SortBy=ItemNumber&SortOrder=Descending
- ercotqueue.com/developer/blue-creek-bess-llc
- interconnectionfyi.substack.com/p/interconnection-weekly-project-updates-442
Commercial operation date: LBNL queue snapshot shows proposed COD of December 1, 2027. No independent news sources or press releases found to validate or contradict this date. ERCOT spreadsheets from mid-2024 show 2026 target, but more recent LBNL data (IA executed Jan 2025) shows 2027, suggesting a schedule slip.
Developer: Only source is LBNL filing entity 'Blue Creek BESS, LLC'. No press releases, corporate announcements, or news coverage found identifying a parent operating company. The LLC name suggests a project-specific entity, but no parent company could be identified from available sources.
Status: Texas PUC Interchange confirms ERCOT Standard Generation Interconnection Agreement (SGIA) executed between CenterPoint Energy Houston Electric, LLC and Blue Creek BESS, LLC on January 8, 2025. LBNL status 'active' with IA executed aligns with regulatory filing.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The proposed Sorghum BESS project is a 208.9 MW battery storage development in Wharton County, Texas. Developed by Blue Creek BESS, LLC, the project entered the ERCOT interconnection queue as ERCOT-26INR0474 on April 15, 2024. The current proposed commercial operation date is December 1, 2027, and the interconnection agreement has been executed.
The project consists solely of battery storage with a total capacity of 208.9 MW. The point of interconnection is the #44060 Blue Substation at 345kV. The project is currently listed as active within the ERCOT queue. Recent news coverage has discussed the project.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wharton
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Blue Creek BESS, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
#44060 Blue Substation 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_HOUSTON
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage pipeline in ERCOT
Data tables and metrics from the InfraSure database.
Battery storage projects in ERCOT
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.