Bologna BESS
202.56 MW storage in Wichita, TX · In queue since March 2024 · Proposed COD April 2028
202.56 MW
Capacity
1
Components
Battery
2y 4m
In Queue
Facility Study
IA Phase
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-19
Entered ERCOT queue, Facility Study stage
The Bologna BESS project is a proposed 202.56 MW battery storage project located in Wichita County, Texas. The project, developed by Maloney BESS LLC, is interconnected within the ERCOT region and entered the ERCOT interconnection queue as queue ID ERCOT-26INR0472 on March 29, 2024. Its proposed commercial operation date is April 19, 2028, and its interconnection status is currently in the Facility Study phase.
The project consists entirely of battery storage, with a total capacity of 202.56 MW. The point of interconnection is Tap 138kV #1450 Pleasant Valley Switch - #1492 Wichita Falls Riverbend. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Wichita
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
MALONEY BESS LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 138kV #1450 Pleasant Valley Switch - #1492 Wichita Falls Riverbend
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Bologna BESSForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.