Hamby Solar
205.8 MW generation in Jones, TX · In queue since March 2024 · Proposed COD June 2028
205.8 MW
Capacity
1
Components
Solar
2y 8m
In Queue
Facility Study
IA Phase
Signed Dec 2025
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
1y 9m
IA → COD
2y 6m
Total Duration
1y 9m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
SS Completed, FIS Started, IA
Project under construction
Typical: 12–24 months
Proposed COD: 2028-06-27
Projected COD moved
1 time
May 2026 → Jun 2028
Net change
+25 months
first report to latest
Capacity
63 → 206 MW
changed in the reports
Latest stage
IA signed
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Target IA execution date per LBNL queue filing, interconnection agreement with AEP Texas
interchange.puc.texas.govProposed commercial operation date confirmed in ERCOT MORA report
ercot.comResearch sources and reasoning (4 recorded sources)
medium confidence at research time
- ercot.com/files/docs/2026/02/05/Capacity-Changes-by-Fuel-Type-Charts_January_2026.xlsx
- interchange.puc.texas.gov/search/filings/?UtilityType=E&ControlNumber=35077&ItemMatch=Equal&DocumentType=ALL&SortBy=FilingParty&SortOrder=Ascending
- images1.showcase.com/d2/-0De-RO-jQonkpQ2jP1NIhlV4X4KhA7CUOhUCTtJjTw/document.pdf
- ercot.com/files/docs/2026/05/01/MORA_July2026.pdf
Commercial operation date: LBNL queue filing shows proposed COD of 2028-06-27. ERCOT capacity charts and MORA reports from early 2026 confirm 2028 target with no contradictory signals from press releases or developer announcements.
Developer: All sources consistently reference 'Abilene GCE LLC' as the developer. No parent company or operating entity identified in search results. PUC filings show interconnection agreements with AEP Texas and Abilene GCE LLC as counterparty.
Status: LBNL shows 'active' status in Facility Study phase. ERCOT MORA report from May 2026 lists project as future capacity for 2028. No withdrawal, cancellation, or construction start signals found.
About
Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Hamby Solar project is a proposed 71.4 MW solar generation facility located in Jones County, Texas. The project, developed by Abilene GCE LLC, is currently in the ERCOT interconnection queue as entry ERCOT-26INR0440, with a queue entry date of March 22, 2024.
The proposed commercial operation date for Hamby Solar is June 27, 2028. Its interconnection status is currently in the Facility Study phase. The point of interconnection is the 6245 ABILENE ROBERTSON PRISON 69 KV.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Jones
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Abilene GCE LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6245 ABILENE ROBERTSON PRISON 138 KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_NORTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Hamby Solar
Data-driven briefing on Hamby Solar — fleet, generation, financial, and news signals.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
RP SCG Texas Solar
Summary analysis with parallel narrative sections and visualizations.
Solar queue pipeline overview
Summary analysis with parallel narrative sections and visualizations.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.