Big Rooter West Storage
201.08 MW generation in Robertson, TX · In queue since March 2024 · Proposed COD December 2028
201.08 MW
Capacity
1
Components
Battery
2y 8m
In Queue
Facility Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
SS Completed, FIS Started, No IA
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Projected COD moved
3 times
Dec 2026 → Dec 2028
Net change
+24 months
first report to latest
Capacity
0 → 201 MW
changed in the reports
Latest stage
Facilities study done
in ERCOT's latest report
Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered ERCOT queue, Facility Study stage
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of December 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity 'Big Rooter West, LLC' is available. No press releases or corporate announcements found to identify a parent operating company. Name pattern suggests project-specific LLC but no parent company identified.
Status: LBNL shows active queue status in Facility Study phase. No news coverage found to indicate project progression beyond interconnection studies.
About
Generated Oct 25, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Big Rooter West Storage is a proposed energy development project in Robertson County, Texas, under development by Big Rooter West, LLC. The project has a total capacity of 201.08 MW. Its interconnection queue record classifies the technology as Solar+Battery, but the only component listed is a 201.08 MW battery energy storage system, which is consistent with the "Storage" designation in the project's name. The project is categorized as a generation project.
The project is in the interconnection queue of the Electric Reliability Council of Texas (ERCOT) under queue ID ERCOT-26INR0432. It entered the queue on March 22, 2024, and its status is active. The proposed point of interconnection is listed as "39950# TNTNP_ONE_3 345 KV," which indicates a connection at the 345 kV transmission level. The project's interconnection agreement status is at the Facility Study stage. The proposed commercial operation date is December 1, 2028.
Summary provenance
Summary generated Oct 25, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- ERCOT queue source as of: Oct 1, 2026.
- Queue history observations through: Sep 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
TX
County
Robertson
Grid Region
ERCOT (Texas)
Market
ISO/RTO Member
Developer
Big Rooter West, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
39950# TNTNP_ONE_3 345 KV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- ERCOT
- Trading Hub
- HB_SOUTH
- Hub Confidence
- LOW
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.