PowerVault BESS (ERCOT-26INR0422) — Project Summary

Queue ID
ERCOT-26INR0422
Capacity
254.8 MW
Technology
Battery
Status
active
Location
Mclennan, TX
Region
ERCOT
Developer
SMT Elm Mott BESS
IA Status
Facility Study

PowerVault BESS

ERCOT-26INR0422BetaActiveBatteryERCOTLBNL + Live

254.8 MW storage in Mclennan, TX · In queue since March 2024 · Proposed COD July 2028

BA: ERCOISO/RTO: ERCOTNERC: TRERC: ERCOT

254.8 MW

Capacity

1

Components

Battery

2y 8m

In Queue

Facility Study

IA Phase

COD target: 2028

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 4m

Facilities Study50%
Queue EntryMar 22, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

SS Completed, FIS Started, No IA

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-01

Queue history
26INR0422 · 30 monthly ERCOT reports, Apr 2024 – Sep 2026

Projected COD moved

1 time

Jul 2027 → Jul 2028

Net change

+12 months

first report to latest

Capacity

255 MW

unchanged in the reports

Latest stage

Screening started

in ERCOT's latest report

Projected COD in each reportDue now (report date = COD)Milestone first reported
Screening study startedMar 22, 2024

Typical ERCOT request: projected COD moved 3 times, net +24 months (median of 2,595 requests whose COD moved). Projected COD is the developer's estimate as reported to ERCOT. Each date links to the ERCOT report it first appeared in. Source: ERCOT Generation Interconnection Status report (GIS, report type 15933).

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Oct 1, 2026 queue source. Research and queue COD differ; this comparison does not confirm either date. See the queue record for reported project facts.

Research COD
Jul 1, 2027
Differs from queue: Jul 1, 2028From queue filing
Developer in saved assessment
Spearmint Energy
Filed as SMT Elm Mott BESS
Status at research time
Active
Active — Facility Study stage, no IA executed yet. Project appears to be in early development with no construction timeline announced.
Financing
Not recorded

Milestones in this assessment

IA executedLatest in this assessment

No IA executed — currently in Facility Study stage per ERCOT queue

ercotqueue.com
Research sources and reasoning (3 recorded sources)

medium confidence at research time

  1. finance.yahoo.com/sectors/energy/articles/spearmint-energy-secures-450-million-160446435.html
  2. ercotqueue.com/project/26INR0422
  3. renewablesinfo.org/project/ercot-26inr0422-powervault-bess

Commercial operation date: Only LBNL queue data provides a COD target of July 2027. No press releases, financing announcements, or news coverage specific to PowerVault BESS were found to validate or update this date.

Developer: LBNL filing uses 'SMT Elm Mott BESS' which matches Spearmint Energy's naming convention ('SMT' prefix). Recent Yahoo Finance article confirms Spearmint Energy closed $450M financing for a Texas BESS project, and the legal entity pattern is consistent with Spearmint's project-LLC structure.

Status: LBNL status is 'Active' at Facility Study stage. No news coverage specific to this project confirms construction start, financing close, or other advancement milestones.

About

Saved background

Generated Apr 10, 2026 · Predates Oct 1, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

PowerVault BESS is a proposed 254.8 MW battery storage project located in McLennan County, Texas. The project, being developed by SMT Elm Mott BESS, entered the ERCOT interconnection queue as project ERCOT-26INR0422 on March 22, 2024. Its proposed commercial operation date is July 1, 2027. The project's interconnection status is currently in the Facility Study phase.

The proposed project consists entirely of battery storage with a total capacity of 254.8 MW. The point of interconnection is Tap 345kV 3406 Elm Mott - 3405 Tradinghouse Ses. Recent news coverage indicates the project has been mentioned in articles related to grid infrastructure.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • ERCOT queue source as of: Oct 1, 2026.
  • Queue history observations through: Sep 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

TX

County

Mclennan

Grid Region

ERCOT (Texas)

Market

ISO/RTO Member

Developer

SMT Elm Mott BESS

Utility

—

Entity

ERCOT

Service Type

—

Point of Interconnection

Tap 345kV 3406 Elm Mott - 3405 Tradinghouse Ses

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
ERCOT
Trading Hub
HB_NORTH
Hub Confidence
MEDIUM
POI Substation
Elm Mott Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.